Final exam
Agile and Scrum Basics
Before you start
- 20 questions, drawn at random from a pool of 35.
- Pass mark: 70%. Your final score is 30% practice + 70% exam.
- No time limit, but finish within 3 hours. You can move between questions before you submit.
- Failed? Review the lessons and try again: every attempt gets a new set of questions.
Question 1 of 20Choose one
For which project is a detailed, plan-everything-first approach most appropriate?
Question 2 of 20True or false
In Agile work, time and cost are often fixed while scope is adjusted to deliver the most valuable features first.
Question 3 of 20Match the pairs
Complete each Agile Manifesto value by matching the left side to what it is valued over.
Tap an answer, then tap the place where it belongs (or drag it there).
- Working software
- Responding to change
- Individuals and interactions
- Customer collaboration
Question 4 of 20Choose one
Which of these is one of the twelve principles behind the Agile Manifesto?
Question 5 of 20What would you do?
What would you do?
A team works 60-hour weeks for two months to hit every sprint commitment, and quality is starting to slip. Which Agile principle is being ignored most directly?
Question 6 of 20Fill in the blanks
Fill in the blanks
Scrum is founded on , the idea that knowledge comes from experience and decisions are made based on what is observed.
Question 7 of 20Put in order
Put the three pillars of empiricism in the order in which they depend on each other.
Drag the items, or use the arrow buttons, to put them in order.
- Adaptation
- Inspection
- Transparency
Question 8 of 20Select all that apply
Which of these are the five Scrum values? Select all that apply.
Select all that apply.
Question 9 of 20True or false
According to the Scrum Guide, a team can drop the Daily Scrum and still be doing Scrum, as long as the other events happen.
Question 10 of 20Sort into groups
Which accountability does each responsibility belong to?
Tap an item, then tap its group (or drag it there).
Question 11 of 20Choose one
What does the Scrum Guide say about the size of a Scrum Team?
Question 12 of 20Choose one
A stakeholder wants a feature moved to the top of the Product Backlog. Whom must they convince?
Question 13 of 20What would you do?
What would you do?
A Scrum Master spends most of each day updating the team's tickets, booking meeting rooms and sending status emails to management. What's the main problem?
Question 14 of 20Match the pairs
Match each artifact to its commitment.
Tap an answer, then tap the place where it belongs (or drag it there).
- Product Backlog
- Sprint Backlog
- Increment
Question 15 of 20True or false
A Scrum Team can deliver an Increment to stakeholders before the Sprint Review.
Question 16 of 20Choose one
Which of these belongs in a team's Definition of Done rather than in one story's acceptance criteria?
Question 17 of 20What would you do?
What would you do?
At the end of a sprint, an item meets its acceptance criteria but hasn't been through the security review that the Definition of Done requires. What happens to it?
Question 18 of 20Choose one
Who has the authority to cancel a sprint, and when?
Question 19 of 20Choose one
What is the maximum timebox for the Daily Scrum?
Question 20 of 20Put in order
Put these Scrum events in the order they occur within a sprint.
Drag the items, or use the arrow buttons, to put them in order.
- Sprint Review
- Sprint Retrospective
- Daily Scrum
- Sprint Planning
Question 21 of 20Spot the mistake
These notes describe a team's Sprint Review. Click each note that shows the review being misused.
Question 22 of 20Choose one
Which question is the Sprint Review designed to help answer?
Question 23 of 20What would you do?
What would you do?
A team's retrospectives always end with a long list of complaints and no agreed action. What should the team change first?
Question 24 of 20Fill in the blanks
Fill in the blanks
Complete the user story template: As a [type of user], I want [some goal], [benefit].
Question 25 of 20Match the pairs
Match each part of an INVEST check to the problem it guards against.
Tap an answer, then tap the place where it belongs (or drag it there).
- Small
- Testable
- Valuable
- Estimable
Question 26 of 20Choose one
Which split of the epic "As a shopper, I want to check out" produces the best vertical slices?
Question 27 of 20Work it out
A release has 168 story points remaining. The team's average velocity is 28 points per sprint. How many sprints will the remaining work take at the average pace?
Question 28 of 20True or false
Story points measure the exact number of hours a story will take.
Question 29 of 20Choose one
In planning poker, why does everyone reveal their estimate at the same time?
Question 30 of 20Sort into groups
For the first release of an online grocery delivery service, which MoSCoW category fits each feature best?
Tap an item, then tap its group (or drag it there).
Question 31 of 20Work it out
Item P has a value score of 8 and an estimate of 2 points. Item Q has a value score of 9 and an estimate of 9 points. What is item P's value-to-effort ratio?
Question 32 of 20Work it out
A Kanban team averages 30 items in progress and finishes 10 items per week. Using Little's Law, what is the average cycle time in weeks?
Question 33 of 20Choose one
A Kanban board's Testing column is full at its WIP limit, and a developer has just finished coding a new item. What should the developer do?
Question 34 of 20Choose one
A release burnup chart shows completed work rising steadily, but the total scope line is rising just as fast. What does this tell you?
Question 35 of 20Select all that apply
Which of these are common Agile anti-patterns? Select all that apply.
Select all that apply.