Final exam
Project Management Fundamentals
Before you start
- 20 questions, drawn at random from a pool of 36.
- Pass mark: 70%. Your final score is 30% practice + 70% exam.
- No time limit, but finish within 3 hours. You can move between questions before you submit.
- Failed? Review the lessons and try again: every attempt gets a new set of questions.
Question 1 of 20Choose one
Which two characteristics define a project?
Question 2 of 20True or false
If a project's deadline is moved earlier and the budget stays the same, the scope or the quality will usually have to change.
Question 3 of 20Match the pairs
Match each project role to its main responsibility.
Tap an answer, then tap the place where it belongs (or drag it there).
- Sponsor
- Project manager
- Team member
- Customer
Question 4 of 20Put in order
Order the process groups for a typical small project.
Drag the items, or use the arrow buttons, to put them in order.
- Closing
- Planning
- Initiating
- Executing
Question 5 of 20What would you do?
What would you do?
A team is building a new mobile game. The publisher wants to test early versions with players every few weeks and expects the features to change based on what players enjoy. Which approach fits best?
Question 6 of 20Sort into groups
Classify each project by the approach that usually fits best.
Tap an item, then tap its group (or drag it there).
Question 7 of 20Choose one
Which objective is written in SMART form?
Question 8 of 20Choose one
On a power/interest grid, how should you treat a stakeholder with high power but low interest, such as a busy CFO?
Question 9 of 20True or false
In a RACI chart, it is good practice to have two people Accountable for an important task so there is a backup.
Question 10 of 20Select all that apply
Which of these are typically included in a project charter? Select all that apply.
Select all that apply.
Question 11 of 20Choose one
Which statement belongs in the exclusions section of a scope statement for a new website?
Question 12 of 20Work it out
A WBS element "Training" is budgeted at $30,000. Its work packages are Course design ($9,000), Materials ($6,000), Trainer fees and Venue ($5,000). Under the 100% rule, how much is Trainer fees?
Question 13 of 20Spot the mistake
Tap the two statements about the WBS that are false.
Question 14 of 20True or false
Scope creep usually happens through one large, formally approved change.
Question 15 of 20Work it out
A task has optimistic, most likely and pessimistic estimates of 2, 4 and 12 days. What is its PERT expected duration?
Question 16 of 20Work it out
Using the same estimates (O = 2, M = 4, P = 12 days), what is the PERT standard deviation? Give one decimal place.
Question 17 of 20Choose one
A company estimates that carpeting a new office will cost $34 per square yard for 1,500 square yards, totaling $51,000. Which technique is this?
Question 18 of 20Choose one
Which dependency type is most common in project schedules?
Question 19 of 20Work it out
Activities: A (2 days, no predecessor), B (4 days, after A), C (7 days, after A), D (3 days, after B), E (1 day, after C and D). What is the project duration?
Question 20 of 20Work it out
An activity has an early start of day 5 and a late start of day 9. How many days of total float does it have?
Question 21 of 20Match the pairs
Match each schedule compression technique to its main drawback.
Tap an answer, then tap the place where it belongs (or drag it there).
- Crashing
- Fast-tracking
- Cutting scope
Question 22 of 20Choose one
Which reserve covers identified risks and is included in the cost baseline?
Question 23 of 20Work it out
A project has PV = $60,000, EV = $54,000 and AC = $48,000. What is the cost variance (CV) in dollars?
Question 24 of 20Work it out
For the same project (PV $60,000, EV $54,000, AC $48,000), what is the SPI? Give two decimal places.
Question 25 of 20Choose one
A project has BAC = $500,000 and CPI = 1.25. What is the EAC if performance continues at this rate?
Question 26 of 20Sort into groups
Sort each item as a risk or an issue.
Tap an item, then tap its group (or drag it there).
Question 27 of 20Work it out
A threat has a 25% probability and would cost $80,000 if it occurred. What is its expected monetary value in dollars (ignore the sign)?
Question 28 of 20Match the pairs
Match each risk response to its example.
Tap an answer, then tap the place where it belongs (or drag it there).
- Avoid
- Mitigate
- Transfer
- Exploit
Question 29 of 20Work it out
A project team grows from 6 to 12 people. How many communication channels are added?
Question 30 of 20Choose one
A project has been reported green for months, but the team privately knows it is three weeks behind. What is this pattern called, and why is it harmful?
Question 31 of 20True or false
A product can be low grade and still high quality.
Question 32 of 20What would you do?
What would you do?
A customer emails the project manager asking to add a reporting dashboard to a system that is already in testing. What should the project manager do first?
Question 33 of 20Choose one
In Scrum, who is responsible for ordering the product backlog?
Question 34 of 20Fill in the blanks
Fill in the blanks
The Daily Scrum is time-boxed to minutes, and a sprint lasts one or less.
Question 35 of 20Choose one
What is the main purpose of a work-in-progress (WIP) limit on a Kanban board?
Question 36 of 20Select all that apply
Which practices make lessons learned more useful? Select all that apply.
Select all that apply.