Module 4: Performance, Breach and RemediesLesson 8 of 1113 min

Performance, Breach and Excuses

Understand conditions, substantial performance, material vs. minor breach, repudiation, and when force majeure or impracticability excuse performance.

Step 1 of 12Learn

Conditions and the order of performance

Contracts often say not just what each party must do, but when and under what conditions.

A condition is an event that must occur before a duty to perform arises. A condition precedent must happen first: "Buyer's obligation to purchase is conditioned on obtaining a mortgage at 7% or less within 30 days." If the buyer, trying in good faith, can't get the mortgage, they don't have to buy. Home purchase contracts commonly include financing, inspection and appraisal contingencies.

A condition subsequent ends an existing duty: "Coverage ends if the insured moves out of state."

Conditions can be express (written in the contract) or implied by courts. When no order is specified, courts apply default rules: in a sale, payment and delivery are expected at the same time; in a service contract, the work usually comes first and payment after.

Every contract also carries an implied covenant of good faith and fair dealing: neither party may act to undermine the other's right to receive the benefits of the deal. A buyer with a financing contingency can't deliberately sabotage their own loan application to escape the purchase. The UCC defines good faith for merchants as honesty in fact plus observance of reasonable commercial standards of fair dealing.

Step 2 of 12Compare

Three kinds of conditions

AspectCondition precedentConcurrent conditionsCondition subsequent
TimingMust happen before a duty arisesBoth sides perform at the same timeEnds a duty that already exists
ExampleBuyer must close only if the inspection is satisfactoryAt closing, the deed is handed over as the price is paidInsurance coverage ends if premiums are not paid
If it failsThe duty never becomes dueNeither side must perform until the other tendersThe duty is discharged

Step 3 of 12Practice · What would you do?

What would you do?

A home purchase contract makes the buyer's duty to close conditional on "obtaining a satisfactory home inspection within 10 days." The inspection reveals a cracked foundation. What can the buyer generally do?

Step 4 of 12Learn

Material breach, minor breach and substantial performance

Not every failure to perform is equal. Contract law distinguishes:

  • Material breach: a failure so serious that it defeats the essential purpose of the contract. The injured party can stop performing, terminate the contract and sue for damages. A caterer who doesn't show up to a wedding has materially breached.
  • Minor (immaterial) breach: a failure that doesn't defeat the main purpose. The injured party must keep performing but can recover damages for the shortfall. A caterer who serves the wrong brand of sparkling water has breached in a minor way.

Courts weigh factors such as how much of the expected benefit was lost, whether money can compensate, whether the breaching party is likely to cure, and whether they acted in good faith.

The related doctrine of substantial performance applies mainly in construction and service contracts. In Jacob & Youngs v. Kent (New York, 1921), a builder accidentally used Cohoes brand pipe instead of the Reading brand the contract required. The pipes were of the same quality. Replacing them would have meant tearing down walls at great expense. Judge Benjamin Cardozo held that the builder had substantially performed and was entitled to payment, minus the difference in value, which was essentially nothing.

For goods under the UCC, the default is the stricter perfect tender rule: the buyer may reject goods that fail to conform to the contract in any respect, though sellers often have a right to cure by delivering conforming goods within the contract time.

Step 5 of 12Compare

Material vs minor breach

AspectMaterial breachMinor breach
Effect on the dealDefeats its essential purposeMain purpose still achieved
ExampleA caterer never shows up for the weddingThe caterer arrives 15 minutes late with everything else right
Injured party may stop performingYes, and may terminateNo; must still perform
DamagesYes, for the whole lossYes, for the shortfall only

Step 6 of 12Practice · Sort into groups

Would each failure most likely be treated as a material breach or a minor breach?

Tap an item, then tap its group (or drag it there).

Step 7 of 12Learn

Anticipatory repudiation and excuses

Anticipatory repudiation happens when, before performance is due, a party clearly states or shows they won't perform: "I'm not going to deliver the furniture in June." The other party doesn't have to wait. They can treat it as a breach immediately, find a substitute and sue, or wait a reasonable time for the repudiating party to retract. Under the UCC, if a party has reasonable grounds for insecurity, it can demand adequate assurance of performance in writing; failure to provide it within a reasonable time, up to 30 days, counts as repudiation.

Sometimes performance is excused by events beyond anyone's control:

  • Impossibility: performance can't be done by anyone, such as when the specific building to be renovated burns down or a singer hired for a concert dies.
  • Impracticability: performance is possible but would be extremely and unreasonably difficult or costly because of an unforeseen event whose non-occurrence was a basic assumption of the contract. Ordinary price increases don't qualify; a 15% rise in costs is a normal business risk.
  • Frustration of purpose: performance is possible, but the reason for the contract has been destroyed. In Krell v. Henry (England, 1903), a man rented a flat to watch King Edward VII's coronation procession. When the coronation was postponed due to the king's illness, the court excused the renter.
  • Force majeure clauses: contracts often list specific events, like natural disasters, war, government orders, epidemics and strikes, that excuse or delay performance. During COVID-19, many disputes turned on the exact wording of these clauses: courts usually required that the event be listed or clearly covered and that it actually prevented performance.

Step 8 of 12Practice · Match the pairs

Match each situation with the doctrine it best illustrates.

Tap an answer, then tap the place where it belongs (or drag it there).

  1. The concert hall booked for a show burns down before the event
  2. A supplier's costs triple after an unforeseen war closes the only shipping route
  3. A rooftop rented solely to watch a parade becomes pointless when the parade is canceled
  4. A seller announces in March it won't deliver in June
  5. A contract lists "pandemics and government shutdown orders" as excusing delay

Step 9 of 12Flashcards

When non-performance may be excused

Tap a card to flip it.

Step 10 of 12Note

Step 11 of 12Practice · True or false

A 15% increase in the cost of materials is usually enough to excuse a seller from performing under the doctrine of impracticability.

Step 12 of 12Practice · Choose one

A builder finishes a house but uses a different, equally good brand of insulation than the contract specified. Replacing it would cost $40,000 and add no real value. What is the owner most likely entitled to?