Buffers: zones of influence
A city plans a new rail station and wants to know how many residents will live within a 10-minute walk, roughly 800 meters. A river protection rule bans construction within 30 m of a stream. A pipeline company must notify everyone within 200 m of a proposed route. All of these use buffers.
A buffer is a polygon enclosing all locations within a specified distance of a feature:
- Around a point, it is a circle (an 800 m buffer around a station).
- Around a line, it is a corridor with rounded ends (30 m on each side of a stream).
- Around a polygon, it is an expanded shape (a 1 km zone around a park), or with a negative distance, a shrunken one.
Options matter:
- Distance units and CRS: buffer in a projected CRS with meters. Buffering in degrees produces distorted, meaningless shapes.
- Multiple ring buffers: concentric zones at several distances, such as 0–500 m, 500–1,000 m and 1,000–1,500 m, useful for distance-decay studies.
- Dissolve: merge overlapping buffers into one zone, or keep them separate to count overlaps.
- Variable distance: buffer each feature by a value in its attribute table, for example wider buffers around larger rivers.
Remember that a buffer measures straight-line (Euclidean) distance. A home 700 m from a station in a straight line may be a 2 km walk if a highway or river blocks the way. For travel distances, network analysis along roads and paths gives more realistic service areas.
Step 2 of 12Try the calculator
Circular buffer area
A point buffer is a circle, so its area is π r². Enter a radius to see the area covered, for example the walking catchment of a station.
- Buffer area
- 2,010,619 m²
- Buffer area
- 201.1 ha
- Buffer area
- 2.011 km²
Step 3 of 12Practice · Work it out
What is the area of a 1,000 m buffer around a single point, in square kilometers? Round to two decimals.
Step 4 of 12Learn
Overlay: combining layers
Overlay combines two or more layers to create a new one that carries information from both. It is one of the most powerful operations in GIS. The main vector overlay tools:
- Intersect: keeps only areas that are in both layers, with attributes from both. Intersecting soil polygons with a farm boundary gives the soil types within the farm.
- Union: keeps all areas from both layers, splitting polygons where they overlap, with attributes from both where they exist.
- Clip: cuts one layer to the shape of another, like a cookie cutter, keeping only the input layer's attributes. Clipping national roads to a county boundary gives the county's roads.
- Erase (difference): removes the parts of one layer that overlap another. Erasing protected areas from a parcel layer leaves only unprotected land.
- Dissolve: merges adjacent polygons that share an attribute value, removing internal boundaries. Dissolving counties by state gives state polygons.
Intersect and clip are often confused. Clip keeps only the attributes of the layer being clipped; the clip layer is just the cutter. Intersect combines attributes from both inputs.
Overlay can create sliver polygons: tiny, thin shapes where two boundaries that should match do not quite align, often because the layers came from different sources or scales. Tolerance settings and careful data preparation reduce slivers.
Raster overlay works cell by cell: if two rasters have the same grid, you can add, multiply or compare their values, which is the basis of map algebra in the next lesson.
Step 5 of 12Practice · Match the pairs
Match each overlay tool with its result.
Tap an answer, then tap the place where it belongs (or drag it there).
- Clip
- Intersect
- Union
- Erase
- Dissolve
Step 6 of 12Note
Step 7 of 12Learn
Site suitability: putting it together
Site suitability analysis finds locations that meet a set of criteria, combining queries, buffers and overlay. Suppose a county wants a site for a new solar farm. Criteria might be:
- Land at least 20 hectares in a single parcel.
- Slope less than 5%.
- Within 2 km of an electrical substation.
- Not in a wetland, flood zone or protected area.
- At least 300 m from homes.
A Boolean (binary) approach treats each criterion as pass/fail:
- Buffer substations by 2 km (criterion 3).
- Buffer homes by 300 m and erase that zone (criterion 5).
- Erase wetlands, flood zones and protected areas (criterion 4).
- Select areas with slope under 5% from a slope raster converted to polygons (criterion 2).
- Intersect all remaining layers, then select resulting parcels of 20 ha or more (criterion 1).
The result is a map of sites that pass every test. Its weakness: a site 2.1 km from a substation fails completely, even if it is perfect otherwise.
A weighted overlay approach scores each criterion on a scale, such as 1 to 10, assigns weights by importance (maybe slope 30%, distance to substation 40%, distance to homes 30%), and adds the weighted scores. Exclusions such as protected areas are still removed absolutely. The result ranks locations from most to least suitable, allowing trade-offs.
Either way, the results depend on the criteria and weights, which are value judgments. Good practice is to document them and test how results change when they change, called sensitivity analysis.
Step 8 of 12Practice · Put in order
Put these steps of a Boolean site suitability analysis in a sensible order.
Drag the items, or use the arrow buttons, to put them in order.
- Create buffers and exclusion zones for each criterion
- Filter results by minimum site size and review them
- Define the criteria with stakeholders
- Overlay the criteria layers to find areas that pass all tests
- Gather and project all layers into the same CRS
Step 9 of 12Diagram
Narrowing down solar farm sites
Tap a shape with to see more.
- All land in the county
- Within 2 km of a substation
- No wetlands, floods, protected land
- At least 300 m from homes
- Slope under 5%
- Parcels of 20 ha or more
The sites that pass every Boolean test.
Step 10 of 12Note
Step 11 of 12Practice · What would you do?
What would you do?
A Boolean suitability analysis rejects a parcel that meets every criterion except that it is 2.05 km from a substation, just outside the 2 km limit. The client is unhappy. What is a sensible improvement?
Step 12 of 12Practice · Choose one
You want the roads that lie inside a national park, and you need only the road attributes. Which tool fits best?