The Control Process
Learn the three steps of control, set acceptable ranges of variation, choose corrective action, and use feedforward, concurrent and feedback controls.
Welcome back!
Step 1 of 12Learn
The thermostat on the wall
A thermostat is a perfect little manager. You set a target temperature (a standard). It measures the room every few minutes, compares the reading with the target, and turns the heat on or off to correct any gap. It doesn't overreact to tiny changes, and it keeps working without being asked.
Controlling is the management function of monitoring activities to make sure they are being done as planned and correcting significant deviations. It is the link that closes the management cycle: without control, managers have no way of knowing whether plans and goals are being met.
The control process has three steps:
- Measure actual performance. Managers gather information through personal observation (walking around), statistical reports, oral reports and written reports. They must decide what to measure: what gets measured tends to get attention, so measuring the wrong thing can push people in the wrong direction.
- Compare actual performance with the standard. Standards come from the goals set in planning. Some deviation is normal, so managers set a range of variation, an acceptable band around the target. Only deviations outside that band call for action.
- Take managerial action. Managers can do nothing (when performance is within range), correct actual performance, or revise the standard.
Skipping control is like setting a thermostat and then removing the sensor. The plan exists, but nobody notices when the room gets cold.
Step 2 of 12Practice · Put in order
Put the steps of the control process in order.
Drag the items, or use the arrow buttons, to put them in order.
- Compare performance with the standard and range of variation
- Take managerial action if needed
- Set standards during planning
- Measure actual performance
Step 3 of 12Diagram
The control loop
Tap a shape with to see more.
- Standard (from planning)
The target set during planning, with an acceptable range.
- Measure
Observation, statistical, oral and written reports.
- Compare
Is the gap outside the range of variation?
- Act
Do nothing, correct performance, or revise the standard.
Step 4 of 12Learn
Taking the right action
Once a significant deviation shows up, managers choose among actions.
Correcting actual performance. The cause might be a poor strategy, inadequate training, broken equipment, low motivation or a bad structure. Managers can take:
- Immediate corrective action: fixing the problem right away to get performance back on track, such as sending extra staff to a backed-up checkout line.
- Basic corrective action: finding out how and why the deviation happened and fixing the source, such as discovering that the checkout delays come from a slow card reader and replacing it.
Many managers stop at immediate fixes because they are busy, "putting out fires" every day without ever asking why fires keep starting. Basic corrective action takes more time but prevents repeat problems.
Revising the standard. Sometimes the standard itself was wrong: set too high, too low, or based on conditions that changed. If an entire sales team misses a target after a major customer goes bankrupt, the target may need adjusting. But managers should be cautious: when people miss a goal, they often blame the standard. Lowering it too easily rewards excuses.
A quick example of the comparison step: a call center's standard is answering calls within 60 seconds, with an acceptable range of ±10%. Average answer time this week is 64 seconds, a 6.7% deviation, within range, so no action is needed. If it reaches 75 seconds (25% over), the manager investigates.
Step 5 of 12Try the calculator
Variance check
Compare actual performance with a standard and see whether the deviation falls outside the acceptable range.
- Deviation
- 4
- Deviation in percent
- 6.7 %
- Margin left within the range (negative = outside)
- 3.3 %
Step 6 of 12Practice · Work it out
A factory's standard is 2,000 units per shift, with an acceptable range of ±5%. Today's shift produced 1,880 units. By what percentage did it fall short of the standard? (Enter a positive number.)
Step 7 of 12Practice · Chart
A week of output against the ±5% range
Standard: 2,000 units. The acceptable range is 1,900 to 2,100. Only one day calls for action.
Tap the day that falls outside the acceptable range.
Tap the point that answers the question, then press Check.
| Item | Actual | Lower limit | Upper limit |
|---|---|---|---|
| Mon | 2,030 | 1,900 | 2,100 |
| Tue | 1,985 | 1,900 | 2,100 |
| Wed | 1,950 | 1,900 | 2,100 |
| Thu | 2,070 | 1,900 | 2,100 |
| Fri | 1,880 | 1,900 | 2,100 |
Step 8 of 12Learn
When to control: before, during and after
Managers can control at three points in the work:
- Feedforward control happens before the work begins, preventing problems. Examples: inspecting raw materials, training new employees before they serve customers, preventive maintenance on aircraft. It is the most desirable type because it stops problems before damage is done, but it requires accurate predictions.
- Concurrent control happens while the work is going on. Examples: a supervisor watching an employee's first calls, software that flags an unusual transaction in real time, "management by walking around." It catches problems before they become costly.
- Feedback control happens after the work is done. Examples: monthly financial reports, customer satisfaction surveys, final product inspection. Its weakness is that the damage has already occurred. Its strengths are that it shows how well planning worked and gives employees information about their performance.
Most organizations use all three. A restaurant inspects deliveries (feedforward), has the chef taste dishes before they leave the kitchen (concurrent) and reviews online reviews and monthly food costs (feedback).
Good control systems share some qualities: they are accurate, timely (information arrives while it can still be used), economical, flexible, understandable, based on reasonable standards and focused on strategic points where problems matter most. They also highlight exceptions rather than burying managers in data on everything that is going fine.
Step 9 of 12Practice · Diagram
When control happens
Which point is cheapest for fixing problems, if you can manage it?
Tap the shape that answers the question, then press Check.
- Feedforward: before
Prevent problems: inspect materials, train staff, maintain equipment.
- Concurrent: during
Catch problems as they happen: supervising, live dashboards.
- Feedback: after
Learn from results: monthly reports, customer surveys.
Step 10 of 12Practice · Sort into groups
Classify each control as feedforward, concurrent or feedback.
Tap an item, then tap its group (or drag it there).
Step 11 of 12Note
Step 12 of 12Practice · What would you do?
What would you do?
A delivery company finds that 8% of packages arrive late, against a standard of 3% (acceptable range up to 4%). The regional manager orders drivers to work overtime for two weeks, and late deliveries fall. A month later they are back at 8%. What should the manager do now?
Lesson complete!