Measuring Results and Making Them Stick

Set a baseline, measure whether a change truly worked, separate its effect from other factors and lock in improvements so the problem does not return.

Step 1 of 14Learn

Did it actually work?

A sales team adopted a new follow-up process in April. By June, sales were up 15%. The team leader presented it as a clear success. Then someone pointed out that sales rose by about the same amount every spring, and that a competitor had gone out of business in May.

So did the new process work? Maybe. But the 15% increase on its own can't tell you. Several things changed at once, and seasonal patterns move results regardless of what you do.

This lesson is about the "Check" in Plan-Do-Check-Act. Measuring results sounds simple: look at the number before, look at it after. In practice, it's easy to fool yourself in both directions, crediting a change for an improvement it didn't cause, or dismissing a good change because its effect was hidden by other factors.

Good measurement does three things. It establishes a clear baseline: where things stood before the change. It uses a metric that actually reflects the problem. And it finds a way to separate the change's effect from everything else happening at the same time.

Then comes the part most teams skip: once you've confirmed a solution works, making sure it keeps working after attention moves on.

Step 2 of 14Practice · Chart

Sales: this year vs last year

Tap the month where the new process started.

Tap the point that answers the question, then press Check.

Sales: this year vs last yearLine chart with 6 categories: Jan: This year (new process from April) 100, Last year (no change) 96; Feb: This year (new process from April) 98, Last year (no change) 95; Mar: This year (new process from April) 102, Last year (no change) 98; Apr: This year (new process from April) 108, Last year (no change) 103; May: This year (new process from April) 113, Last year (no change) 108; Jun: This year (new process from April) 117, Last year (no change) 111.95100105110115120Sales indexJanFebMarAprMayJunMonth
Illustrative data: both years rise in spring, so the before/after jump overstates the effect.
Sales: this year vs last year
MonthThis year (new process from April)Last year (no change)
Jan10096
Feb9895
Mar10298
Apr108103
May113108
Jun117111

Step 3 of 14Practice · True or false

If a result improves after a change, the change must have caused the improvement.

Step 4 of 14Learn

Baselines and metrics

Measure before you change. A baseline is the level of your key metric before any change, measured over a long enough period to capture normal variation. One good week isn't a baseline. Two to four weeks of data, or the same period last year for seasonal businesses, is far more reliable.

Choose metrics that match the problem. The metric should come straight from your problem statement. If the problem was "patients wait 38 minutes past their appointment time," the metric is average delay past appointment time, not "number of appointments" or "staff satisfaction," however useful those are.

Two kinds of metrics help:

  • Outcome metrics (lagging indicators) measure the result you care about: wait time, defect rate, complaints. They're the ultimate test but can take time to move.
  • Process metrics (leading indicators) measure whether the change is actually happening: the percentage of appointments with buffers, the share of patients who completed paperwork online. If the process metric doesn't move, the outcome can't either.

Also watch a balancing metric: something that could get worse as a side effect. If you shorten call times, track repeat calls. If you speed up production, track defects.

Calculate improvement clearly: percent change = (after − before) ÷ before × 100. A wait time dropping from 38 to 14 minutes is a 63% reduction.

Step 5 of 14Practice · Work it out

A help desk's average ticket resolution time drops from 50 hours to 32 hours after a process change. What is the percentage reduction?

Step 6 of 14Practice · Match the pairs

A clinic adds buffer slots to reduce patient delays. Match each metric to its type.

Tap an answer, then tap the place where it belongs (or drag it there).

  1. Average minutes patients wait past their appointment time
  2. Percentage of daily schedules that include the buffer slots
  3. Number of patients seen per day

Step 7 of 14Learn

Separating the effect from the noise

How do you know a change caused an improvement? Several approaches, from simple to rigorous:

Look at a run chart. Plot the metric over time, week by week, with a line marking when the change happened. A sustained shift after the change, especially one larger than normal week-to-week ups and downs, is more convincing than a single before-and-after comparison. A common rule of thumb in quality improvement: six or more points in a row on the same side of the baseline average suggests a real shift rather than chance.

Compare with a similar group. If one clinic adopts the change and three similar clinics don't, compare their trends. If the pilot clinic improved and the others didn't, the change is the likely cause. If all four improved, something else is probably going on.

Compare with the same period last year. For seasonal patterns, this removes much of the confusion.

Turn it off and on. In some cases you can remove the change briefly and see if the problem returns. If it does, and improves again when the change is restored, the evidence is strong.

Randomized tests. Where possible, randomly assign which customers, orders or sites get the change. Websites routinely do this as A/B testing. Randomization is the most reliable way to isolate an effect, because other factors balance out across groups.

Step 8 of 14Chart

A run chart with a real shift

A run chart with a real shiftLine chart with 12 categories: W1: Average wait 38 min, Baseline average 38.5 min; W2: Average wait 41 min, Baseline average 38.5 min; W3: Average wait 36 min, Baseline average 38.5 min; W4: Average wait 40 min, Baseline average 38.5 min; W5: Average wait 39 min, Baseline average 38.5 min; W6: Average wait 37 min, Baseline average 38.5 min; W7: Average wait 30 min, Baseline average 38.5 min; W8: Average wait 28 min, Baseline average 38.5 min; W9: Average wait 31 min, Baseline average 38.5 min; W10: Average wait 27 min, Baseline average 38.5 min; W11: Average wait 29 min, Baseline average 38.5 min; W12: Average wait 28 min, Baseline average 38.5 min.25 min30 min35 min40 min45 minMinutes past appointmentW1W2W3W4W5W6W7W8W9W10W11W12Week
Illustrative. Change made after week 6; six points in a row below the baseline suggests a real shift.
A run chart with a real shift
WeekAverage waitBaseline average
W138 min38.5 min
W241 min38.5 min
W336 min38.5 min
W440 min38.5 min
W539 min38.5 min
W637 min38.5 min
W730 min38.5 min
W828 min38.5 min
W931 min38.5 min
W1027 min38.5 min
W1129 min38.5 min
W1228 min38.5 min

Step 9 of 14Practice · Diagram

Strength of evidence for a change

Tap the method that best balances out all other factors.

Tap the shape that answers the question, then press Check.

Strength of evidence for a changePyramid diagram: Before/after comparison, Same period last year, Run chart, sustained shift, Compare with similar group, Turn it off and on, Randomized test (A/B).Before/after comparisonSame period last yearRun chart, sustained shiftCompare with similar groupTurn it off and onRandomized test (A/B)
From weakest (bottom) to strongest (top), roughly.
Before/after comparison
Same period last year
Run chart, sustained shift
Compare with similar group
Turn it off and on
Randomized test (A/B)

Step 10 of 14Practice · What would you do?

What would you do?

A retail chain introduced a new staff scheduling method at 10 of its 40 stores in October. Sales at those 10 stores rose 8% in the following two months. What additional information would best show whether the scheduling method caused the rise?

Step 11 of 14Learn

Make it stick

Problems that were "solved" often quietly return. People drift back to old habits, new staff aren't trained on the new way, a tool falls out of use, and a year later the problem is back. Making gains stick requires deliberate work, sometimes called the control or sustain phase.

Standardize. Update written procedures, checklists, templates and system settings so the new way is the documented way. If the old form still exists, people will use it; remove it.

Train and onboard. Add the new method to training for new staff. A surprising number of improvements disappear simply because the people who learned them moved on.

Build it into the system. Wherever possible, make the new way automatic: the buffer slot is a default in the scheduling software, the form won't submit without the required field. Error-proofing beats reminders here too.

Keep measuring. Continue tracking the key metric, perhaps less often. Set a threshold that triggers a review: "If average delay rises above 20 minutes for two weeks in a row, the clinic manager investigates."

Assign an owner. One person is responsible for the process going forward.

Share what you learned. Write a short summary: the problem, the causes, the solution, the results. Other teams facing similar problems can start from your work instead of from scratch.

Step 12 of 14Tap to reveal

A 30-60-90 day sustain check

  1. Day 30

    Is the process metric holding? Are people using the new method, or drifting back? Fix any practical obstacles you find.

  2. Day 60

    Has the outcome metric stayed improved? Check the balancing metric for side effects. Confirm new staff were trained on the new way.

  3. Day 90

    If results are stable, reduce monitoring to monthly, hand the process to its long-term owner and write the lessons-learned summary.

Step 13 of 14Practice · Select all that apply

Which actions help ensure an improvement lasts? Select all that apply.

Select all that apply.

Step 14 of 14Practice · Work it out

Before a change, a factory's defect rate was 4.0% of units. After the change, it is 2.5%. What is the percentage reduction in the defect rate?