Capacity Factor and Keeping the Lights On
Calculate capacity factor, see why the grid must balance supply and demand every second, and learn how variable solar and wind are managed.
Welcome back!
Step 1 of 11Learn
Rated power isn't the whole story
A news story says a new 100 MW solar farm is as big as a 100 MW gas plant. Is it? Not in energy terms. The solar farm only reaches 100 MW around noon on clear days. At night it makes nothing.
Engineers capture this with the capacity factor: the energy a plant actually produces over a year, divided by what it would make running at full power all year.
capacity factor = actual energy ÷ (rated power × hours)
A year has 8,760 hours. A 2 MW wind turbine running flat out all year would make 2 × 8,760 = 17,520 MWh. If it actually produces 6,132 MWh, its capacity factor is 6,132 ÷ 17,520 = 35%.
Typical ranges:
| Source | Typical capacity factor |
|---|---|
| Solar PV | about 10–30%, depending on location |
| Onshore wind | about 25–45% |
| Offshore wind | about 40–55% |
| Hydropower | about 35–55% |
| Geothermal | about 70–90% |
| Nuclear | about 90% |
A low capacity factor isn't a failure. It just means you need more installed capacity to produce the same energy, and you need a plan for the hours when output is low.
Step 2 of 11Try the calculator
Capacity factor calculator
A year has 8,760 hours (365 × 24).
- Maximum possible energy per year
- 17,520 MWh
- Capacity factor
- 35 %
Step 3 of 11Practice · Work it out
A 5 MW solar farm produces 8,760 MWh in a year. What is its capacity factor, in percent?
Step 4 of 11Chart
Typical capacity factors
Step 5 of 11Learn
Balancing the grid every second
The electric grid connects power plants to homes and businesses through high-voltage transmission lines and local distribution lines. It has a strict rule: supply must match demand every second. If demand exceeds supply, the grid's frequency drops, and in serious cases operators must cut power to some areas to prevent a wider blackout.
Demand follows a daily rhythm: low at night, rising in the morning, often peaking in the early evening as people come home, cook and turn on lights and air conditioning. Solar output peaks at midday and fades just as that evening peak arrives. Plot the demand left over after solar, and you get a curve with a deep midday dip and a steep evening climb that grid engineers call the duck curve, because it looks like a duck's back and neck.
Wind is less predictable hour to hour, but forecasting has become very accurate a day or two ahead. Grid operators use those forecasts to plan which other sources to run.
Variable sources like solar and wind aren't unreliable in the sense of breaking down. They are reliably affected by weather. The task is to fill the gaps.
Step 6 of 11Practice · Chart
The duck curve
Tap the time when demand left after solar is at its peak, after the steepest climb.
Tap the point that answers the question, then press Check.
| Item | Total demand | Demand left after solar |
|---|---|---|
| Midnight | 22 GW | 22 GW |
| 3 am | 20 GW | 20 GW |
| 6 am | 23 GW | 22 GW |
| 9 am | 27 GW | 17 GW |
| Noon | 28 GW | 11 GW |
| 3 pm | 29 GW | 14 GW |
| 6 pm | 33 GW | 29 GW |
| 9 pm | 30 GW | 30 GW |
Step 7 of 11Tap to reveal
Five ways to handle variable solar and wind
Mix sources
Wind often blows more at night and in winter, when solar is weak. Combining them smooths total output.
Connect wide areas
Long transmission lines link regions with different weather. It's rarely calm and cloudy everywhere at once.
Flexible plants
Hydro dams, and for now gas plants, can ramp up quickly when solar and wind fall short.
Storage
Batteries and pumped hydro store surplus energy and release it later. Covered in the next lesson.
Demand response
Shift flexible demand, such as charging electric cars or heating water, to times when renewable power is plentiful.
Step 8 of 11Practice · Choose one
A 100 MW solar farm (capacity factor 20%) and a 100 MW geothermal plant (capacity factor 90%) are built. Over a year, how do their energy outputs compare?
Step 9 of 11Practice · True or false
On a power grid, electricity supply must match demand from moment to moment.
Step 10 of 11Practice · What would you do?
What would you do?
An island runs on diesel generators and wants to switch to renewables. It has strong trade winds day and night and lots of sunshine. What is the most reliable plan?
Step 11 of 11Practice · Fill in the blanks
Fill in the blanks
Capacity factor equals the energy actually produced divided by rated power times the number of . One year contains hours.
Lesson complete!