Module 3: Sourcing and ProcurementLesson 5 of 1213 min

Sourcing and Supplier Selection

Weigh make-or-buy decisions, compare suppliers on total cost of ownership rather than price, and score them with a weighted decision matrix.

Step 1 of 11Learn

The cheapest quote that cost a fortune

A kitchen appliance maker needed 50,000 plastic housings a year. Its local supplier charged $8.00 each. An overseas supplier quoted $7.20, a 10% saving worth $40,000 a year. The buyer switched and was praised in the quarterly review.

A year later the numbers looked different. Ocean freight and port fees added $1.10 per unit, import duty added 5% of the price, and because shipping took six weeks instead of three days, the company had to hold far more inventory, costing about $0.30 per unit a year to finance and store. Two late shipments stopped the assembly line. Once the dust settled, each housing cost nearly $9.00.

The lesson is the core of modern sourcing: price is not cost. Total cost of ownership (TCO) adds every cost of getting a part from a supplier into use:

  • purchase price
  • freight, insurance, duties and customs brokerage
  • inventory carrying cost caused by long or unreliable lead times
  • quality costs: inspection, scrap, rework and returns
  • administration: managing the supplier, travel, audits
  • risk: the expected cost of disruptions

TCO doesn't always favor the local supplier. Often the overseas option still wins. The point is to compare suppliers on the full picture, not on the number at the top of the quote.

Step 2 of 11Practice · Chart

Price is not cost: one plastic housing

Which supplier is really cheaper per unit?

Tap the bar that answers the question, then press Check.

Price is not cost: one plastic housingStacked bar chart with 2 categories: Local supplier: Purchase price $8, Freight and port fees $0, Import duty (5%) $0, Extra inventory carrying $0; Overseas supplier: Purchase price $7.2, Freight and port fees $1.1, Import duty (5%) $0.36, Extra inventory carrying $0.3.$0$2$4$6$8$10Cost per unitLocal supplierOverseas supplier$8$8.96
From the appliance maker story; line stoppages from late shipments are not even included.
Price is not cost: one plastic housing
ItemPurchase priceFreight and port feesImport duty (5%)Extra inventory carrying
Local supplier$8$0$0$0
Overseas supplier$7.2$1.1$0.36$0.3

Step 3 of 11Try the calculator

Landed cost comparison

Compare two suppliers per unit. Duty is a percentage of the purchase price; carrying cost covers the extra inventory you hold because of the lead time.

Supplier A total per unit
8.5 $
Supplier B total per unit
8.96 $
Yearly saving by choosing A (negative = B is cheaper)
23,000 $

Step 4 of 11Practice · Work it out

A supplier quotes $20.00 per unit. Freight adds $1.50 per unit, import duty is 4% of the price, and inspection and scrap cost about $0.70 per unit. What is the landed cost per unit before carrying costs?

Step 5 of 11Learn

Make or buy?

Before choosing a supplier, a company decides whether to buy the item at all. The make-or-buy decision weighs several factors:

  • Core competence: Is this something that makes us special? A smartphone company may design its own chips because they set its products apart, but buy screws and cables.
  • Cost: Compare the full cost of making (materials, labor, equipment, overhead, management time) with the TCO of buying. Be careful with overhead: if the factory's rent is paid either way, it shouldn't count against making.
  • Capacity and capability: Do we have the skills, equipment and space? Building them takes time and capital.
  • Control and risk: Making protects secrets and quality; buying adds dependence on a supplier but spreads risk and frees capital.
  • Volume and flexibility: A specialist supplier serving many customers often reaches economies of scale a single buyer can't.

When buying, companies also choose where. Offshoring moves supply to distant low-cost countries; nearshoring moves it to nearby countries (for a US firm, perhaps Mexico); reshoring brings it back home. After the disruptions of the early 2020s, many companies began weighing lead time and resilience more heavily against labor cost, so nearshoring has become a common option rather than an exception.

Step 6 of 11Practice · Sort into groups

Would most companies lean toward making or buying in each case?

Tap an item, then tap its group (or drag it there).

Step 7 of 11Learn

Scoring suppliers with a weighted matrix

When several suppliers qualify, a weighted scoring matrix keeps the choice objective.

  1. List the criteria that matter, such as quality, total cost, delivery reliability, capacity, financial health and service.
  2. Give each criterion a weight so the weights add up to 100%.
  3. Score each supplier on each criterion, for example 1 to 5.
  4. Multiply each score by its weight and add them up.

Suppose weights are quality 40%, cost 30%, delivery 20% and service 10%. Supplier X scores 4, 3, 5, 4: total = 0.4×4 + 0.3×3 + 0.2×5 + 0.1×4 = 1.6 + 0.9 + 1.0 + 0.4 = 3.9. Supplier Y scores 3, 5, 3, 3: total = 1.2 + 1.5 + 0.6 + 0.3 = 3.6. X wins even though Y is cheaper, because this buyer values quality and delivery most.

The matrix is only as good as its weights, so agree on them before seeing supplier scores. Setting weights after you already have a favorite turns the tool into a justification exercise. Many teams also add knock-out criteria: requirements such as a safety certification or minimum capacity that a supplier must meet just to be considered.

Step 8 of 11Practice · Work it out

Weights: quality 50%, cost 30%, delivery 20%. A supplier scores quality 4, cost 2 and delivery 5 on a 1–5 scale. What is its weighted score?

Step 9 of 11Note

Step 10 of 11Compare

Single, sole and multiple sourcing

AspectSingle sourcingSole sourcingMultiple sourcing
MeaningChoosing one supplier even though others existOnly one supplier in the world can provide the itemSplitting volume across two or more suppliers
AdvantagesVolume discounts, deep partnership, consistent qualityAccess to unique technology or patentsBackup if one fails, price competition
RisksTotal dependence if that supplier has a problemNo alternative; weak negotiating positionLess volume each, more management work, possible quality variation

Step 11 of 11Practice · What would you do?

What would you do?

A medical device maker buys a critical valve from one supplier that delivers excellent quality at a fair price. A fire at the supplier's only plant would stop the device maker's production for months. What is the most balanced response?