Step 1 of 12Learn

The $2 million study that should not count

A sportswear company spent $2 million last year on market research for a new trail-running shoe. The research is done and paid for. Now management must decide whether to launch the shoe, which needs $15 million of new equipment. Should the $2 million be included in the project's NPV?

No. The money is gone whether or not the shoe is launched. It is a sunk cost, and including it would make a good project look worse for no reason. The question is always: what changes for the firm if we take the project versus if we do not? Only those changes, the incremental cash flows, belong in the analysis.

That principle sorts out most tricky cases:

  • Opportunity costs count. If the shoe will be made in a building the firm already owns but could rent out for $400,000 a year, that lost rent is a real cost of the project.
  • Side effects count. If the new shoe will steal some sales from the company's existing road shoe (cannibalization), those lost profits reduce the project's cash flows. Positive spillovers, such as more store traffic, count too.
  • Allocated overhead usually does not count, unless the project actually causes overhead to rise. Moving a share of the CEO's salary onto the project changes no cash flows.
  • Financing costs do not count in the cash flows. Interest and dividends are captured in the discount rate.

Step 2 of 12Practice · Sort into groups

For the trail-shoe decision, sort each item into relevant (include in project cash flows) or not relevant.

Tap an item, then tap its group (or drag it there).

Step 3 of 12Flashcards

Relevant or not? The cost traps

Tap a card to flip it.

Step 4 of 12Learn

Operating cash flow and the depreciation tax shield

Each year of a project produces operating cash flow (OCF): the after-tax cash from running it. There are two equivalent ways to compute it.

Top-down from EBIT: OCF = EBIT × (1 − t) + depreciation

Tax-shield approach: OCF = (revenue − cash costs) × (1 − t) + depreciation × t

The second version shows something important. Depreciation is not a cash cost, but it reduces taxable income. Each dollar of depreciation saves t dollars of tax. That saving, depreciation × t, is the depreciation tax shield.

Example: a project brings in revenue of $500,000 with cash costs of $300,000 and depreciation of $80,000, at a 25% tax rate.

  • Top-down: EBIT = $500k − $300k − $80k = $120k. Tax = $30k. OCF = $90k + $80k = $170k.
  • Tax shield: ($200k × 0.75) + ($80k × 0.25) = $150k + $20k = $170k.

Faster depreciation schedules do not change the total depreciation, but they bring the tax shield forward in time. Because earlier savings are worth more, accelerated depreciation raises NPV. This is one reason governments sometimes use bonus depreciation to encourage investment. Rules differ by country, so models should follow the tax code that actually applies.

Step 5 of 12Practice · Work it out

A project has annual revenue of $800,000, cash operating costs of $500,000 and depreciation of $100,000. The tax rate is 21%. What is its annual operating cash flow, in dollars?

Step 6 of 12Try the calculator

Operating cash flow calculator

See how the depreciation tax shield adds to operating cash flow. Amounts in thousands of dollars.

EBIT
120 $k
After-tax operating profit
90 $k
Depreciation tax shield
20 $k
Operating cash flow
170 $k

Step 7 of 12Learn

Working capital and salvage value

Two more cash flows often get forgotten.

Net working capital. A new product line usually needs inventory, and customers buying on credit create receivables. That investment is a cash outflow at the start, and often more each year as sales grow. When the project ends and inventory is sold off and receivables collected, the working capital is recovered as a cash inflow. Because the recovery comes years later, working capital has a real cost in present-value terms even if every dollar returns.

Salvage value. Equipment may be sold at the end of a project. What matters is the after-tax salvage value:

After-tax salvage = sale price − t × (sale price − book value)

If you sell for more than the asset's remaining book value, you pay tax on the gain. If you sell for less, the loss reduces taxes. Example: equipment sold for $50,000 with a book value of $20,000 at a 25% tax rate brings in $50,000 − 0.25 × $30,000 = $42,500.

Putting it together, a project's yearly free cash flow is:

FCF = OCF − capital spending − change in NWC

with the initial investment and NWC in year 0, and after-tax salvage plus NWC recovery in the final year. Laying these out in a timeline table, year by year, is the standard way to build a project model.

Step 8 of 12Chart

A project's cash flows by type

A typical project: big outflows for equipment and working capital up front, operating cash flow during its life, and two inflows at the end when working capital is recovered and the equipment is sold.

A project's cash flows by typeBar chart with 5 categories: Year 0: Equipment (capex / after-tax salvage) -$500, Net working capital -$50, Operating cash flow $0; Year 1: Equipment (capex / after-tax salvage) $0, Net working capital $0, Operating cash flow $150; Year 2: Equipment (capex / after-tax salvage) $0, Net working capital $0, Operating cash flow $160; Year 3: Equipment (capex / after-tax salvage) $0, Net working capital $0, Operating cash flow $160; Year 4: Equipment (capex / after-tax salvage) $40, Net working capital $50, Operating cash flow $150.-$600-$400-$200$0$200$ thousandsYear 0Year 1Year 2Year 3Year 4
Illustrative project.
A project's cash flows by type
ItemEquipment (capex / after-tax salvage)Net working capitalOperating cash flow
Year 0-$500-$50$0
Year 1$0$0$150
Year 2$0$0$160
Year 3$0$0$160
Year 4$40$50$150

Step 9 of 12Practice · Work it out

At the end of a project, equipment with a book value of $30,000 is sold for $45,000. The tax rate is 21%. What is the after-tax salvage cash flow, in dollars?

Step 10 of 12Tap to reveal

Four ways to stress-test a forecast

  1. Sensitivity analysis

    Change one input at a time, such as sales volume, price or cost per unit, and see how NPV moves. Inputs that swing NPV the most deserve the most research.

  2. Scenario analysis

    Change several inputs together to build coherent stories: a pessimistic case (low volume, low price), a base case and an optimistic case. Scenarios capture inputs that tend to move together.

  3. Break-even analysis

    Find the value of a key input, often sales volume, at which NPV equals zero. Managers can then judge how likely it is that reality falls below that level.

  4. Monte Carlo simulation

    Assign a probability distribution to each uncertain input and let software run thousands of trials. The output is a distribution of NPVs instead of a single number.

Step 11 of 12Practice · True or false

When estimating a project's cash flows, you should subtract the interest on any debt used to finance it.

Step 12 of 12Practice · Choose one

A company is deciding whether to open a new store in a building it already owns. The building is currently empty but could be leased to another business for $120,000 a year. How should this be treated in the store's NPV analysis?