Why managers love a percentage
Ask a room of managers whether a project with an NPV of $3.2 million is good, and many will hesitate. Tell them it earns 18% a year and the cost of capital is 10%, and heads nod. Percentages feel intuitive. That is why the internal rate of return (IRR) is one of the most widely used tools in business, alongside NPV.
The IRR is the discount rate that makes a project's NPV exactly zero:
0 = C₀ + C₁ / (1 + IRR) + C₂ / (1 + IRR)2 + … + Cₙ / (1 + IRR)n
On the NPV profile from the previous lesson, IRR is where the curve crosses the horizontal axis.
The IRR rule says: accept a project if its IRR exceeds the cost of capital. For a conventional project, an outflow followed by inflows, this gives the same accept-or-reject answer as NPV. If the IRR is 15.2% and the cost of capital is 10%, NPV at 10% is positive.
Except in simple cases, IRR has no closed-form solution. Spreadsheets and calculators find it by trial and error. For a two-period example, though, you can solve it directly: a project costing $1,000 that pays $1,210 in two years has (1 + IRR)2 = 1.21, so IRR = 10%.
Step 2 of 12Practice · Work it out
A project costs $5,000 today and pays a single $6,050 at the end of year 2, with nothing in between. What is its IRR, in percent?
Step 3 of 12Learn
Where IRR goes wrong
IRR and NPV agree on independent, conventional projects. They can disagree badly in three situations.
1. Mutually exclusive projects of different size. A small project might earn 40% on $100,000 (NPV $50,000) while a large one earns 20% on $10 million (NPV $1.5 million). IRR prefers the small one; owners would rather have the extra $1.45 million. When you must choose one, pick the higher NPV.
2. Different timing. A project that pays back quickly can have a higher IRR but a lower NPV than one whose cash arrives later, especially at low discount rates. Again, NPV gives the right ranking because it measures dollars of value at the actual cost of capital.
3. Non-conventional cash flows. If the signs of the cash flows change more than once, for example an upfront cost, years of inflows, then a large cleanup cost at the end, the NPV curve can cross zero twice. Such a project has two IRRs, and neither tells you what to do. Some projects have no real IRR at all.
IRR also implicitly assumes interim cash flows can be reinvested at the IRR itself, which is optimistic for very high-IRR projects. The modified IRR (MIRR) fixes this by assuming reinvestment at the cost of capital. Practical takeaway: report IRR if your audience likes it, but make decisions with NPV.
Step 4 of 12Practice · Chart
NPV profiles of a small and a large project
Small: invest $10,000, receive $13,000 in one year (IRR 30%). Large: invest $50,000, receive $20,000 a year for four years (IRR about 22%). IRR favors the small project, but at any discount rate below about 22% the large one adds more value.
If the cost of capital is 10%, tap that rate and decide: which project should a firm that can do only one choose?
Tap the point that answers the question, then press Check.
| Discount rate | Small project | Large project |
|---|---|---|
| 0% | $3,000 | $30,000 |
| 5% | $2,381 | $20,919 |
| 10% | $1,818 | $13,397 |
| 15% | $1,304 | $7,100 |
| 20% | $833 | $1,775 |
| 25% | $400 | -$2,768 |
| 30% | $0 | -$6,675 |
Step 5 of 12Practice · What would you do?
What would you do?
An energy company must pick one of two mutually exclusive plant designs, both with a 10% cost of capital. Design X costs $20 million, has an IRR of 24% and an NPV of $6 million. Design Y costs $60 million, has an IRR of 16% and an NPV of $11 million. Which should it choose?
Step 6 of 12Learn
Payback and discounted payback
The payback period asks how long it takes for a project's cash inflows to recover its initial cost. It is popular because it is easy to explain and highlights how quickly cash comes back, which matters to firms worried about liquidity or rapidly changing technology.
Example: a project costs $70,000 and produces $15,000, $20,000, $25,000 and $30,000 in years 1 to 4. After three years, $60,000 has come back. The remaining $10,000 is a third of year 4's $30,000, so payback is about 3.33 years.
Payback has serious flaws:
- It ignores the time value of money: a dollar in year 3 counts the same as a dollar in year 1.
- It ignores everything after the cutoff. A project that pays back in 4 years and then earns nothing looks the same as one that pays back in 4 years and then earns for 20 more.
- The cutoff itself (say, 3 years) is arbitrary.
The discounted payback period fixes the first flaw by using discounted cash flows. It is always longer than ordinary payback. But it still ignores cash flows after the cutoff, so it can reject valuable long-lived projects such as research programs or infrastructure. Use payback as a secondary risk indicator, not as the main decision rule.
Step 7 of 12Practice · Work it out
A machine costs $90,000 and generates cash flows of $25,000, $30,000, $40,000 and $40,000 in years 1 to 4. What is its payback period, in years? Give one decimal place.
Step 8 of 12Practice · Chart
Cumulative cash flow of the $90,000 machine
Payback is where the cumulative line crosses zero. Notice that the simple payback ignores the time value of money and everything after the crossing.
Tap the first year that ends with a positive cumulative cash flow.
Tap the point that answers the question, then press Check.
| Item | Cumulative cash flow |
|---|---|
| Year 0 | -$90,000 |
| Year 1 | -$65,000 |
| Year 2 | -$35,000 |
| Year 3 | $5,000 |
| Year 4 | $45,000 |
Step 9 of 12Learn
The profitability index and capital rationing
Sometimes a firm has more positive-NPV projects than money. A division may be given a fixed budget, or a start-up may be unable to raise more capital for now. This is capital rationing, and it changes the question from "which projects create value?" to "which combination creates the most value within the budget?"
The profitability index (PI) helps here:
PI = PV of future cash flows / initial investment
A PI above 1 means positive NPV. A project with a PI of 1.3 creates 30 cents of value for every dollar invested.
Under a single-period budget limit, ranking projects by PI and funding from the top down gets you close to the best combination. Suppose the budget is $10 million and you have project P (cost $6m, NPV $2.4m, PI 1.40), Q (cost $4m, NPV $1.4m, PI 1.35) and R (cost $10m, NPV $3.0m, PI 1.30). R alone has the biggest NPV, but P plus Q uses the same $10 million and produces $3.8 million.
PI has the same weakness as IRR for mutually exclusive projects without a budget limit: it ignores scale. And if several resources are limited or the limit lasts several years, firms use more formal optimization. But as a quick tool for stretching a fixed budget, PI is very useful.
Step 10 of 12Compare
Investment rules compared
| Aspect | NPV | IRR | Payback | Profitability index |
|---|---|---|---|---|
| Uses time value of money | Yes | Yes | No (discounted payback: yes) | Yes |
| Uses all cash flows | Yes | Yes | No, ignores flows after cutoff | Yes |
| Handles scale | Yes, measured in dollars | No, a rate | No | No, a ratio |
| Best use | Main decision rule | Communicating returns; checking against cost of capital | Liquidity and risk screen | Ranking projects under a budget limit |
| Main pitfall | Needs a good discount rate estimate | Misranks exclusive projects; multiple IRRs | Rejects long-lived value creators | Misranks exclusive projects without a budget limit |
Step 11 of 12Practice · Work it out
A project requires an investment of $400,000. The present value of its future cash flows, at the cost of capital, is $520,000. What is its profitability index?
Step 12 of 12Practice · Choose one
Which investment rule is most likely to reject a valuable 25-year infrastructure project whose biggest cash flows arrive late?