Find a course

Module 3: Capital BudgetingLesson 5 of 1314 min

Net Present Value

Use the NPV rule to decide whether a project creates value, build an NPV profile, and avoid the spreadsheet trap that misplaces the initial investment.

Step 1 of 12Learn

A machine that pays for itself, or does it?

A bakery chain is considering a new automated oven line. It costs $100,000 today and should cut labor and energy costs by $30,000 a year for five years, after which it will be worn out with no resale value.

The plant manager's pitch is simple: "We spend $100,000 and save $150,000. That's a $50,000 gain." But that adds dollars from five different years as if they were the same thing. The last $30,000 arrives five years from now and is worth much less than $30,000 today.

The right question is: is the present value of the savings greater than the cost? Suppose the chain's investors expect 10% a year on projects of this risk. The savings form a 5-year annuity, so their present value is:

$30,000 × [1 − 1.10^−5] / 0.10 = $30,000 × 3.7908 = $113,724

Subtract the $100,000 cost and you get +$13,724. That figure is the project's net present value. The oven is worth buying, but the real gain is about $13,700 in today's money, not $50,000.

If investors instead required 18%, the present value of the savings would fall to about $93,800, and the same oven would destroy value. The cash flows did not change; the opportunity cost did.

Step 2 of 12Chart

The oven project: cash flows vs their present values

Each $30,000 saving is worth less in today's money the later it arrives. The present values add up to $113,724, against a $100,000 cost.

The oven project: cash flows vs their present valuesBar chart with 5 categories: Year 1: Cash saving $30,000, Present value at 10% $27,273; Year 2: Cash saving $30,000, Present value at 10% $24,793; Year 3: Cash saving $30,000, Present value at 10% $22,539; Year 4: Cash saving $30,000, Present value at 10% $20,490; Year 5: Cash saving $30,000, Present value at 10% $18,628.$0$10k$20k$30kYear 1Year 2Year 3Year 4Year 5$30k$27.3k$30k$24.8k$30k$22.5k$30k$20.5k$30k$18.6k
The oven project: cash flows vs their present values
ItemCash savingPresent value at 10%
Year 1$30,000$27,273
Year 2$30,000$24,793
Year 3$30,000$22,539
Year 4$30,000$20,490
Year 5$30,000$18,628

Step 3 of 12Learn

The NPV rule

Net present value (NPV) is the present value of all a project's cash flows, inflows positive and outflows negative, discounted at the opportunity cost of capital:

NPV = C₀ + C₁ / (1 + r) + C₂ / (1 + r)2 + … + Cₙ / (1 + r)n

C₀ is usually negative: the initial investment.

The decision rule is short:

  • NPV > 0: accept. The project earns more than investors could get elsewhere at the same risk, and the NPV is the amount by which it increases the firm's value.
  • NPV < 0: reject. Investors would be better off with the cash in their own hands.
  • NPV = 0: the project earns exactly the required return. It neither creates nor destroys value.

NPV is the preferred rule in corporate finance for good reasons. It uses cash flows, not accounting profit. It accounts for timing through discounting and for risk through the discount rate. And NPVs are additive: the value of two independent projects together is the sum of their NPVs, which makes it easy to evaluate portfolios of projects.

A useful way to think about NPV: if the bakery's shares are fairly priced, announcing the oven project should, in principle, raise the total market value of the company by about $13,724.

Step 4 of 12Practice · Work it out

A project costs $250,000 today and will produce $70,000 at the end of each year for 5 years. The cost of capital is 12%. What is its NPV, in dollars?

Step 5 of 12Explore

NPV profile

The curve plots NPV (in $) against the discount rate x (in %) for a project with an upfront cost I and equal annual inflows C for n years. Where the curve crosses zero is the project's internal rate of return.

-100,000-50,000050,000100,000150,000 102030
NPV at 10%
13,724 $
Undiscounted total gain
50,000 $

Step 6 of 12Practice · Estimate

Use the NPV profile with the default inputs ($100,000 cost, $30,000 a year for 5 years). At roughly what discount rate does NPV fall to zero?

7.5 %

Step 7 of 12Learn

Uneven cash flows

Real projects rarely produce identical cash flows each year. A new product might start slowly, peak in years three and four, then fade. In that case there is no shortcut; you discount each year separately and add them up.

Consider a software upgrade costing $50,000 that produces savings of $20,000 in year 1, $25,000 in year 2 and $15,000 in year 3. At an 8% cost of capital:

YearCash flowDiscount factorPresent value
0−$50,0001.0000−$50,000
1$20,0000.9259$18,519
2$25,0000.8573$21,433
3$15,0000.7938$11,907
NPV$1,859

The project adds about $1,859 of value. Laying the calculation out as a table like this is good practice even when you use a spreadsheet: it makes timing assumptions visible and errors easier to catch.

In most models, cash flows are assumed to arrive at the end of each year. Cash that arrives smoothly through the year is sometimes discounted using mid-year timing, which raises NPV a little. Whatever convention you choose, use it consistently across the projects you compare.

Step 8 of 12Diagram

The NPV recipe

The same five steps work for even or uneven cash flows. Tap each step.

The NPV recipeProcess diagram: Forecast incremental cash flows → Pick the discount rate → Discount each cash flow → Add up, including year 0 → Accept if NPV > 0.Forecastincremental cashflowsPick the discountrateDiscount each cashflowAdd up, includingyear 0Accept if NPV > 0

Tap a shape with to see more.

Forecast incremental cash flows

Only cash that changes because of the project, year by year.

Pick the discount rate

The return investors could earn on investments of the same risk.

Discount each cash flow

Divide the year-t cash flow by (1 + r)t.

Add up, including year 0

The upfront cost enters as a negative, undiscounted number.

Accept if NPV > 0

A positive NPV means the project earns more than the cost of capital and adds value.

Step 9 of 12Practice · Work it out

A project costs $40,000 today and returns $15,000 at the end of year 1, $20,000 at the end of year 2 and $12,000 at the end of year 3. The cost of capital is 10%. What is the NPV, in dollars? Round to the nearest dollar (it may be negative).

Step 10 of 12Note

Step 11 of 12Practice · What would you do?

What would you do?

A city transit company has room in its budget for only one of two mutually exclusive projects of similar risk. Project A (new ticketing app) costs $2 million and has an NPV of $0.6 million. Project B (bus depot upgrade) costs $9 million and has an NPV of $1.4 million. Which should it choose if it can raise the money for either?

Step 12 of 12Practice · Choose one

A project has a negative NPV at the firm's 9% cost of capital. What does this mean?