Module 5: Beyond the RooftopLesson 10 of 1014 min

From Contract to Switch-On and Beyond

Follow a solar project from site survey to permission to operate, and see how solar works together with an EV, heat pump and smart home.

Step 1 of 12Learn

Why it takes months, not days

Priya signed her solar contract in March. The crew installed the panels in a single day in May. The system was switched on in late June. Why did a one-day installation take three months from signature to sunshine?

Most of the time goes into steps that happen on paper, not on the roof. A typical US residential project moves through these stages:

  1. Site survey: a technician measures the roof, checks its structure and condition, inspects the electrical panel and records shading.
  2. Design and engineering: the final layout, string or microinverter design, structural calculations and electrical drawings.
  3. Permitting: the city or county building department reviews the plans for electrical, structural and fire code compliance. Some jurisdictions approve in a day using online tools such as NREL's SolarAPP+; others take weeks.
  4. Utility interconnection application: the utility must approve connecting the system to its grid, especially to check that local transformers can handle the exports.
  5. Installation: racking, panels, inverters, wiring and any battery, usually one to three days.
  6. Inspection: a local inspector checks the finished work against the approved plans and codes.
  7. Permission to operate (PTO): the utility gives final approval, sometimes after installing a new bidirectional meter. Only then should the system be switched on.

Turning the system on before PTO can violate the interconnection agreement and, under some rules, cost you export credits. Good installers handle permits and paperwork for you and keep you informed at each stage.

Step 2 of 12Practice · Put in order

Put the stages of a typical residential solar project in order.

Drag the items, or use the arrow buttons, to put them in order.

  1. Utility permission to operate
  2. Site survey
  3. Installation
  4. Permit and utility interconnection applications
  5. Local inspection
  6. Design and engineering

Step 3 of 12Timeline

Priya's project, signature to sunshine

  1. Early March
    Contract signed
  2. March
    Site survey and design

    Roof, structure, electrical panel and shade are measured; the layout is engineered.

  3. April
    Permit and interconnection applications

    The building department and the utility review the plans.

  4. May
    Installation day

    The crew installs everything in a single day.

  5. Early June
    Inspection

    A local inspector checks the work against the approved plans.

  6. Late June
    Permission to operate

    The utility approves, and only now is the system switched on.

Step 4 of 12Learn

Installation day

On installation day, a crew of two to five people typically:

  • Sets up fall protection and safety equipment on the roof.
  • Locates rafters and attaches mounts (flashings and brackets) with lag bolts into the roof structure. Each penetration is sealed with metal flashing and sealant to prevent leaks. This is the step where workmanship matters most for your roof's long-term health.
  • Bolts rails to the mounts, or uses rail-less systems that attach panels directly.
  • Runs wiring and installs panel-level electronics if used, then mounts the panels and connects them.
  • Installs the inverter, AC and DC disconnect switches, conduit to the main electrical panel, and production monitoring equipment.
  • Connects the system to your electrical panel through a dedicated breaker, or sometimes through a "line-side tap" if the panel is too small.

Electrical panel capacity often surprises homeowners. US electrical code limits how much solar can feed into a panel based on its busbar rating. Older homes with 100-amp panels may need an upgrade to 200 amps, adding cost, especially if an EV charger or heat pump is also planned. Some newer approaches, like smart panels and load management devices, can avoid an upgrade.

Ask your installer how they will route conduit and where the inverter and disconnects will go, since these are visible on the outside of your house. After the job, check that the crew cleaned up, take photos of the system and keep all documentation, warranties and monitoring login details in one place.

Step 5 of 12Practice · Choose one

Which installation step matters most for preventing roof leaks?

Step 6 of 12Learn

Solar in an electrified home

Solar delivers the most value when it works together with other electric technologies:

  • Electric vehicle: charging at home from solar during the day, or from stored battery energy, turns sunlight into miles. An EV driven 12,000 miles a year needs roughly 3,000–4,000 kWh, which about 2.5–3 kW of extra panels can supply in an average US location. Smart chargers can follow solar output, charging faster when panels produce more.
  • Heat pump: replacing a gas or oil furnace with a heat pump raises electricity use, but solar can cover much of the added load, especially for cooling in summer, when solar production and air conditioning demand peak together.
  • Heat pump water heater: can be scheduled to heat water at midday, storing solar energy as hot water in its tank.
  • Home battery: stores midday surplus for evening use and provides backup.
  • Smart home energy management: apps and smart panels can shift flexible loads to sunny hours and shed big loads during outages.

Under net billing rules, these midday loads raise self-consumption and the value of each solar kWh. Under net metering, they matter less financially but still reduce strain on the grid during the evening peak.

A useful mental model is to treat your home as a small energy system: panels supply, batteries and tanks store, and appliances, the car and heating use energy, ideally at the right times. Planning these upgrades together, especially the electrical panel capacity, avoids paying for the same electrical work twice.

Step 7 of 12Practice · Diagram

Your home as a small energy system

Which part stores energy without being a battery?

Tap the shape that answers the question, then press Check.

Your home as a small energy systemParts diagram: Home energy system, Solar panels, Home battery, Heat pump water heater, Electric vehicle, Heat pump, Smart panel or app.Home energysystemSolar panelsHome batteryHeat pumpwater heaterElectricvehicleHeat pumpSmart panelor app
Home energy system
Solar panels

Supply energy while the sun shines.

Home battery

Stores electricity for evenings and outages.

Heat pump water heater

Stores energy as hot water in its tank.

Electric vehicle

A large, flexible load; some can also power the home.

Heat pump

Heating and cooling; summer cooling lines up with solar output.

Smart panel or app

Shifts flexible loads and sheds big ones during outages.

Step 8 of 12Try the calculator

Extra solar for an electric car

Estimate the additional panels needed to cover a car's yearly charging.

Charging energy per year
3,600 kWh
Extra solar capacity needed
2.77 kW
Extra panels
7 panels

Step 9 of 12Practice · Work it out

An EV is driven 10,000 miles a year at 0.32 kWh per mile. The location's specific yield is 1,280 kWh per kW per year. How many kW of extra solar would cover its charging?

Step 10 of 12Note

Step 11 of 12Practice · Select all that apply

Which loads are good candidates to run at midday to increase self-consumption of solar power? Select all that apply.

Select all that apply.

Step 12 of 12Practice · True or false

A homeowner should switch on a new solar system as soon as installation is finished, even before the utility grants permission to operate.