Module 3: Scrum EventsLesson 7 of 1213 min

Daily Scrum, Sprint Review and Retrospective

Run a focused 15-minute Daily Scrum, turn the Sprint Review into a real working session with stakeholders, and make retrospectives produce improvements.

Step 1 of 13Learn

The Daily Scrum: 15 minutes to adapt the plan

The Daily Scrum is a 15-minute event for the Developers, held at the same time and place every working day of the sprint to reduce complexity. Its purpose is to inspect progress toward the Sprint Goal and adapt the Sprint Backlog as necessary, adjusting the upcoming planned work.

If the Product Owner or Scrum Master are actively working on Sprint Backlog items, they participate as Developers. Otherwise, the event belongs to the Developers.

The Developers can use any structure they want, as long as it focuses on the Sprint Goal and produces an actionable plan for the next day. Many teams once used three questions: What did I do yesterday? What will I do today? Is anything blocking me? The 2020 Scrum Guide dropped them because they encouraged individual status reports instead of a team conversation about the goal. A popular alternative is to "walk the board" from right to left, asking what it will take to finish the items closest to Done.

The Daily Scrum is not:

  • A status report to a manager or the Scrum Master
  • The only time the Developers talk. Detailed discussions happen right after, with only the people who need to be involved
  • A problem-solving session. Problems are noted and solved afterward

Step 2 of 13Practice · Spot the mistake

Here are snippets from one team's Daily Scrum. Click the ones that show the event drifting away from its purpose.

Step 3 of 13Learn

The Sprint Review: a working session, not a show

The Sprint Review is held near the end of the sprint to inspect the outcome of the sprint and determine future adaptations. The Scrum Team presents the results of their work to key stakeholders, and progress toward the Product Goal is discussed. The timebox is a maximum of four hours for a one-month sprint.

The Scrum Guide is clear that the Sprint Review should not be limited to a presentation. It's a working session:

  • Stakeholders see and try the Increment, not slides about it.
  • The team discusses what was accomplished and what changed in the environment, such as new competitors, budget changes or user feedback.
  • Together, attendees collaborate on what to do next.

The main output is a revised Product Backlog that reflects what was learned. For the fitness app, stakeholders might try the new booking flow, notice that members want to book recurring classes, and the Product Owner moves recurring bookings up the backlog.

A review that's just a polished demo followed by polite applause wastes its potential. The question to keep asking is: given what we now know, what's the most valuable thing to do next? Inviting real users, or people who talk to them daily, like support staff, makes the review far more useful.

Step 4 of 13Practice · Choose one

What is the main output of a Sprint Review?

Step 5 of 13Diagram

A Sprint Review as a working session

A Sprint Review as a working sessionProcess diagram: Show the Increment → Gather feedback → Discuss what changed → Update the backlog.Show theIncrementGatherfeedbackDiscuss whatchangedUpdate thebacklog

Tap a shape with to see more.

Show the Increment

Working results, not slides. Stakeholders try the product.

Gather feedback

What works, what is missing, what surprised people.

Discuss what changed

Market, budget, timeline and new opportunities.

Update the backlog

The Product Backlog is adjusted to reflect what was learned.

Step 6 of 13Learn

The Sprint Retrospective: improving how the team works

The Sprint Retrospective concludes the sprint. Its purpose is to plan ways to increase quality and effectiveness. The timebox is a maximum of three hours for a one-month sprint.

The Scrum Team inspects how the last sprint went with regard to individuals, interactions, processes, tools and their Definition of Done. They discuss what went well, what problems they encountered and how those problems were or weren't solved. Then they identify the most helpful changes to improve their effectiveness. The most impactful improvements are addressed as soon as possible, and may even be added to the Sprint Backlog for the next sprint.

Where the Sprint Review asks are we building the right thing?, the Retrospective asks are we working the right way?

Retrospectives fail in predictable ways:

  • Same complaints, no action. The team lists problems every sprint but never commits to a change. Pick one or two concrete improvements, with an owner, and check on them next time.
  • No safety. If people fear blame, they stay quiet and the real issues never surface. What's said in the retro should be about the system, not about punishing people.
  • Skipped when busy. The busiest sprints are exactly when a retrospective is most needed.

Varying the format keeps retrospectives fresh and draws out different perspectives.

Step 7 of 13Tap to reveal

Four retrospective formats

  1. Start, Stop, Continue

    Each person notes what the team should start doing, stop doing and keep doing. Simple, fast and good for new teams.

  2. Mad, Sad, Glad

    Team members share what frustrated them, what disappointed them and what pleased them. Surfaces feelings and morale, not just process.

  3. 4Ls: Liked, Learned, Lacked, Longed for

    Encourages reflection on learning and on what the team wished it had, which often reveals missing skills or tools.

  4. Sailboat

    Draw a boat: wind (what pushed us forward), anchors (what held us back), rocks (risks ahead) and the island (our goal). Good for visual teams and for looking ahead as well as back.

Step 8 of 13Practice · Match the pairs

Match each event to its maximum timebox for a one-month sprint.

Tap an answer, then tap the place where it belongs (or drag it there).

  1. Sprint Planning
  2. Daily Scrum
  3. Sprint Review
  4. Sprint Retrospective
  5. Sprint

Step 9 of 13Practice · Work it out

For a one-month sprint, what is the maximum combined number of hours for Sprint Planning, the Sprint Review and the Sprint Retrospective?

Step 10 of 13Chart

Maximum timeboxes for a one-month sprint

Maximum timeboxes for a one-month sprintBar chart with 4 categories: Sprint Planning: 8 h; Sprint Review: 4 h; Sprint Retrospective: 3 h; Daily Scrum (each day): 0.25 h.0 h2 h4 h6 h8 hSprint Planning8 hSprint Review4 hSprint Retrospective3 hDaily Scrum (each day)0.25 h
Upper limits from the Scrum Guide; shorter sprints usually need less.
Maximum timeboxes for a one-month sprint
ItemMaximum hours
Sprint Planning8 h
Sprint Review4 h
Sprint Retrospective3 h
Daily Scrum (each day)0.25 h

Step 11 of 13Note

Step 12 of 13Practice · What would you do?

What would you do?

For four sprints in a row, the retrospective has raised the same issue: code reviews take days, which stalls work. Everyone agrees it's a problem, and nothing changes. As the Scrum Master, what's the most effective next step?

Step 13 of 13Practice · Choose one

Which question is the Sprint Retrospective mainly designed to answer?