The Sprint and Sprint Planning
Learn the rules of the Sprint, who can cancel one, and how Sprint Planning turns a Product Backlog into a Sprint Goal and a realistic plan.
Welcome back!
Step 1 of 12Learn
The heartbeat of Scrum
Every Scrum team runs on a steady rhythm: the Sprint. A sprint is a fixed-length period of one month or less in which the team turns ideas into value. All the other Scrum events happen inside it, and a new sprint begins immediately after the previous one ends.
Two weeks is the most common length, but one, three or four weeks are also used. Whatever the length, it stays consistent. A fixed rhythm makes planning predictable, lets stakeholders know when they'll see progress, and gives the team a natural cadence for inspecting and adapting.
The Scrum Guide sets four rules for what happens during a sprint:
- No changes are made that would endanger the Sprint Goal.
- Quality does not decrease.
- The Product Backlog is refined as needed.
- Scope may be clarified and renegotiated with the Product Owner as more is learned.
Notice the balance. The goal is protected, so the team can focus, but the exact scope isn't frozen. If the team learns that a planned item is far bigger than expected, they talk with the Product Owner and adjust what they build, while still aiming at the why.
Shorter sprints mean faster feedback and less risk per sprint, at the cost of more frequent planning.
Step 2 of 12Learn
Choosing a length, and cancelling a sprint
How long should sprints be? Consider how quickly things change. If the market, users or priorities shift weekly, a four-week sprint means a lot of work aimed at a target that has already moved. If stakeholders can only meet monthly, very short sprints may outrun feedback. The Scrum Guide's limit is one month, because longer sprints let the goal go stale, complexity grow and risk accumulate. Many teams start with two weeks and adjust after a few retrospectives.
A sprint can be cancelled, but only in one situation: when the Sprint Goal becomes obsolete. Imagine the company decides to discontinue the fitness app's group-booking feature midway through a sprint whose goal was group booking. Continuing would waste effort.
Only the Product Owner has the authority to cancel a sprint. Stakeholders, managers or the Scrum Master may suggest it, but the decision rests with the PO. When a sprint is cancelled, any Done work is reviewed and the rest returns to the Product Backlog. Then the team starts a new Sprint Planning.
Cancellation is rare and disruptive. Frequent cancellations usually signal unstable priorities or sprints that are too long.
Step 3 of 12Chart
Chances to inspect and adapt per year
Each sprint ends with a Review and a Retrospective. Shorter sprints mean more feedback points, but each one carries some fixed overhead.
Step 4 of 12Practice · True or false
The Scrum Master can cancel a sprint if the team is falling behind.
Step 5 of 12Learn
Sprint Planning: three questions
Sprint Planning starts the sprint. The whole Scrum Team attends, and they may invite others to provide advice. The timebox is a maximum of eight hours for a one-month sprint, and usually shorter for shorter sprints. Planning addresses three topics:
Topic one: Why is this sprint valuable? The Product Owner proposes how the product could increase its value in this sprint. The whole team then collaborates to define a Sprint Goal that communicates why the sprint is valuable to stakeholders. The Sprint Goal must be finalized before the end of Sprint Planning.
Topic two: What can be done this sprint? The Developers select items from the Product Backlog to include, discussing them with the Product Owner. Refinement during this conversation can increase understanding and confidence.
Topic three: How will the chosen work get done? For each selected item, the Developers plan the work needed to create an Increment that meets the Definition of Done. Often they break items into smaller work items of a day or less. How this is done is up to the Developers alone.
The Sprint Goal, the selected items and the plan together make up the Sprint Backlog. A well-refined Product Backlog makes planning dramatically faster: if the top items are already clear and estimated, planning is a conversation, not an interrogation.
Step 6 of 12Practice · Put in order
Put the three topics of Sprint Planning in the order the Scrum Guide presents them.
Drag the items, or use the arrow buttons, to put them in order.
- How: Developers plan the work to create a Done Increment
- What: Developers select Product Backlog items to include
- Why: agree on a Sprint Goal that explains the sprint's value
Step 7 of 12Diagram
Sprint Planning in three topics
Tap a shape with to see more.
- Why: the Sprint Goal
The Product Owner proposes how the sprint could add value; the whole team shapes a Sprint Goal.
- What: select items
Developers pick Product Backlog items that serve the goal and fit their capacity.
- How: plan the work
Developers break items into work of a day or less, at least for the first days.
Step 8 of 12Learn
How much work fits in a sprint?
Only the Developers decide how much work they can take on. That isn't arbitrary: they're the ones who will do it, and commitments forced on a team by someone else tend to be missed.
The Developers usually consider three inputs:
- Past performance. How much did the team complete in recent sprints? Teams using story points look at their average velocity, covered later in this course.
- Capacity. Who's available? Vacations, holidays, training and support duties reduce what fits. A team with two members out for half the sprint shouldn't plan for a full sprint's work.
- The Definition of Done. All the work to meet it, including testing, review and documentation, has to fit, not just the "main" work.
A common rule of thumb is to plan for about 70–80% of available hours, because meetings, email, support questions and interruptions consume the rest. A team that plans every hour as productive is planning to fail.
It's also normal not to plan every detail. The Developers need enough of a plan to start and to be confident about the Sprint Goal. The rest of the plan emerges during the sprint, and the Daily Scrum is where it gets adjusted.
Step 9 of 12Try the calculator
Sprint capacity calculator
Estimate the realistic number of focused hours available to the team in a sprint.
- Available person-days
- 56
- Focused hours for sprint work
- 336 hours
- Capacity compared with a full sprint
- 93 %
Step 10 of 12Practice · Work it out
A team averages 30 story points per sprint with everyone present. Next sprint, holidays and vacations mean only 80% of the usual person-days are available. Roughly how many points is it reasonable to plan for?
Step 11 of 12Practice · What would you do?
What would you do?
At Sprint Planning, the Product Owner insists the team take on 45 points of work. The Developers' average velocity is 28, and they believe about 30 is realistic. What should happen?
Step 12 of 12Practice · Choose one
Which of these must be finalized by the end of Sprint Planning?
Lesson complete!