Kanban: Visualize Work and Limit WIP

Use a Kanban board to visualize work, set WIP limits so work finishes faster, and measure flow with cycle time, throughput and Little's Law.

Step 1 of 13Learn

Everything started, nothing finished

An IT support team of five handles requests from across the company: new laptops, access permissions, broken printers, software installs. Everyone is busy all day. Yet requesters complain that simple tasks take weeks, and the team can't say when anything will be finished.

When the team lead finally writes every open request on a sticky note and puts them on a wall, the picture is startling: 43 requests in progress at once. Each person is juggling eight or nine, switching between them as people chase updates. Every switch costs time to remember where things stood, and items wait for days while their owner works on something else.

This is the problem Kanban addresses. Kanban, from a Japanese word meaning roughly "visual signal" or "card," grew out of Toyota's production system and was adapted for knowledge work in the 2000s. It's a method for managing and improving the flow of work. It doesn't prescribe roles, sprints or events. Instead it asks a team to make its work visible, limit how much is in progress, and keep improving how smoothly items move from request to done.

It works especially well for continuous, interrupt-driven work like support, operations and maintenance, though many product teams use it too.

Step 2 of 13Learn

The Kanban board and core practices

The central tool is a Kanban board: columns representing the stages work passes through, and cards representing work items. A simple board might have To Do, In Progress and Done; a software team's board might have Backlog, Ready, In Development, Code Review, Testing and Done. Cards move from left to right.

Kanban practices typically include:

  • Visualize the workflow. Every item is on the board, so the real state of work is transparent.
  • Limit work in progress (WIP). Each column, or the whole board, has a maximum number of items.
  • Manage flow. Watch how items move, spot where they get stuck and act on bottlenecks.
  • Make policies explicit. Write down the rules, such as what "Ready" means or which requests count as urgent.
  • Implement feedback loops. Hold regular reviews of the board and the metrics.
  • Improve collaboratively. Make small, evolutionary changes based on data.

A key difference from Scrum: Kanban is pull-based and continuous. There's no sprint commitment. When a person finishes an item and the next column has room, they pull the next highest-priority item. New urgent work can be added to the top of the queue at any time.

Step 3 of 13Practice · Put in order

Put these columns of a typical software team's Kanban board in left-to-right order.

Drag the items, or use the arrow buttons, to put them in order.

  1. Ready
  2. Backlog
  3. Code Review
  4. Testing
  5. In Development
  6. Done

Step 4 of 13Diagram

A software team’s board with WIP limits

A software team’s board with WIP limitsProcess diagram: Backlog → Ready (limit 5) → In development (limit 3) → Code review (limit 2) → Testing (limit 2) → Done.BacklogReady (limit 5)In development (limit 3)Code review (limit 2)Testing (limit 2)Done

Tap a shape with to see more.

Limits are illustrative; each team sets its own.
Backlog

Unlimited pool of ideas.

Ready (limit 5)

Clear enough to start.

In development (limit 3)
Code review (limit 2)
Testing (limit 2)
Done

Step 5 of 13Learn

Why limiting WIP makes work faster

It feels backward: to get more done, start less. But it's one of the most reliable findings in managing flow.

Suppose a developer has three tasks of five days each. Working on all three at once, switching daily, all three finish around day 15, and probably later, because every switch wastes time. Working on them one at a time, the first finishes on day 5, the second on day 10 and the third on day 15. Same total effort, but two items are delivered much sooner, and their users get value earlier.

A WIP limit caps how many items can be in a column at once. If Code Review has a limit of 3 and already holds 3 items, nobody can move another card into it. Instead of starting new work, developers help clear the review queue. The slogan is "stop starting, start finishing."

WIP limits also expose problems. If items pile up in Testing and the limit keeps blocking development, the team has found its bottleneck. Adding more development work wouldn't help; increasing testing capacity, or having developers help test, would.

There's no perfect limit. Teams often start at about one or two items per person in each active stage, then adjust based on what they observe.

Step 6 of 13Practice · Chart

Three 5-day tasks: when does each finish?

Which task gains the most by working one at a time?

Tap the bar that answers the question, then press Check.

Three 5-day tasks: when does each finish?Bar chart with 3 categories: Task A: Switching daily between all three 15, One at a time 5; Task B: Switching daily between all three 15, One at a time 10; Task C: Switching daily between all three 15, One at a time 15.051015Day finishedTask ATask BTask C15515101515
Ideal case with no switching cost; real switching makes the first series even later.
Three 5-day tasks: when does each finish?
ItemSwitching daily between all threeOne at a time
Task A155
Task B1510
Task C1515

Step 7 of 13Practice · True or false

Raising WIP limits so that people can start more items at once is the most reliable way to finish work faster.

Step 8 of 13Learn

Measuring flow: cycle time, throughput and Little's Law

Kanban teams track a few simple metrics:

  • Cycle time: how long an item takes from when work starts until it's done.
  • Lead time: how long from when an item is requested until it's done. This is what the customer experiences, including time waiting in the queue.
  • Throughput: how many items are finished per unit of time, for example 12 per week.
  • WIP: how many items are in progress right now.

These are connected by Little's Law, a result from queueing theory that holds for stable systems over time:

Average cycle time = Average WIP ÷ Average throughput

For the support team: 43 items in progress, finishing about 15 per week, gives an average cycle time of 43 ÷ 15 ≈ 2.9 weeks. That's why simple requests took weeks.

The formula shows the two levers. You can increase throughput, which usually requires more people or better processes, or you can reduce WIP, which costs nothing. If the team cut WIP to 15 while still finishing 15 per week, average cycle time would drop to about one week.

Teams often plot cycle times on a chart to make forecasts like 85% of requests finish within 6 days, which is more useful to customers than an average.

Step 9 of 13Try the calculator

Little's Law calculator

See how work in progress and throughput determine how long items take on average.

Average cycle time
2.9 weeks
Average cycle time in working days
14.3 days

Step 10 of 13Practice · Work it out

A team has an average of 20 items in progress and finishes an average of 5 items per week. According to Little's Law, what is the average cycle time in weeks?

Step 11 of 13Compare

Scrum vs. Kanban

AspectScrumKanban
CadenceFixed-length sprints of one month or lessContinuous flow, no required iterations
RolesProduct Owner, Scrum Master, DevelopersNo required roles
PlanningSprint Planning sets a Sprint GoalItems are pulled when capacity frees up
Limiting workSprint scope limits work per sprintExplicit WIP limits per stage
Key metricsVelocity, burndown, Sprint Goal achievedCycle time, throughput, WIP
Changing prioritiesUsually wait for the next sprint unless the goal is affectedCan change at any time for items not yet started
Good fitProduct development with regular review cyclesSupport, operations and interrupt-driven work

Step 12 of 13Practice · What would you do?

What would you do?

A team's Kanban board shows 9 cards waiting in Testing, which has a WIP limit of 4 that everyone ignores, while developers keep starting new features. Cycle time has doubled. What's the best change?

Step 13 of 13Practice · Choose one

Which statement best describes how Kanban differs from Scrum?