Module 5: Control and SustainLesson 11 of 1214 min

Control Charts and Control Plans

Read control charts, calculate control limits, apply the out-of-control rules, and build a control plan that stops an improved process slipping back.

Step 1 of 11Learn

Why improvements fade

A distribution center cut picking errors from 3% to 0.8% with new bin labels and a scanning step. Six months later, errors were back at 2.5%. Nobody decided to go back. New staff were never shown the scanning step, a broken scanner wasn't replaced for weeks, and the labels on new bins were handwritten again.

This is the most common way improvements fail: not with a bang, but with slow drift. The Control phase exists to prevent it. Its tools answer three questions:

  1. How will we know if the process starts to slip? Monitoring, usually with control charts.
  2. What will we do when it does? A response plan, with named owners.
  3. How will the new way become normal? Updated standard work, training, mistake-proofing and handover to the process owner, the person responsible for the process after the project team moves on.

The best controls don't rely on vigilance. Mistake-proofing (the scanner won't confirm a pick from the wrong bin) beats an instruction (please check the bin number), which beats a reminder poster. When choosing controls, aim as high on that ladder as you reasonably can.

The project isn't complete when the pilot succeeds. It's complete when the process owner has run the new process for a while, results are stable, and monitoring is in place.

Step 2 of 11Chart

Picking errors: improved, then slipping back

Picking errors: improved, then slipping backLine chart with 7 categories: Before: 3%; After fix: 0.8%; Month 2: 0.9%; Month 3: 1.2%; Month 4: 1.6%; Month 5: 2.1%; Month 6: 2.5%.0%1%2%3%BeforeAfter fixMonth 2Month 3Month 4Month 5Month 6
Start, improved and month-6 values from the example; months in between illustrative.
Picking errors: improved, then slipping back
ItemError rate
Before3%
After fix0.8%
Month 20.9%
Month 31.2%
Month 41.6%
Month 52.1%
Month 62.5%

Step 3 of 11Learn

Reading a control chart

A control chart plots a process measure over time, in order, with three horizontal lines:

  • the center line: the process average;
  • the upper control limit (UCL): typically the average + 3 standard deviations of the plotted statistic;
  • the lower control limit (LCL): the average − 3 standard deviations.

The limits are calculated from the process data. They describe what the process actually does, the voice of the process. They are not specification limits, which come from the customer, the voice of the customer. A process can be perfectly in control and still produce out-of-spec output if its natural spread is wider than the specification.

When all points vary randomly within the limits with no unusual patterns, the process is in statistical control: only common-cause variation is present, and it's predictable. Leave it alone; reacting to individual points is tampering.

A point outside the limits, or a non-random pattern, signals a special cause that should be investigated. Common rules (variations of the Western Electric rules) include:

  • one point beyond either control limit;
  • a run of points on one side of the center line, often 8 in a row (some guides use 7 or 9);
  • a trend of 6 or more points steadily rising or falling;
  • unusual patterns such as cycles or points hugging the limits.

Because about 99.7% of common-cause points fall within 3σ, a point beyond the limits by chance happens only about 3 times in 1,000.

Step 4 of 11Try the calculator

Control limit calculator

Enter the average and standard deviation of the plotted statistic, calculated from stable historical data.

Upper control limit (mean + 3σ)
56
Lower control limit (mean − 3σ)
44
Width between the limits
12

Step 5 of 11Practice · Work it out

A process averages 120 seconds per transaction, and the standard deviation of the plotted values is 6 seconds. What is the upper control limit in seconds?

Step 6 of 11Practice · Spot the mistake

A supervisor reviews 12 daily averages from a control chart with center line 50, UCL 56 and LCL 44. Tap the day that, on its own, signals a special cause by the one-point rule.

Step 7 of 11Compare

Common types of control charts

AspectData typeExample use
I-MR (individuals and moving range)Continuous, one measurement at a timeDaily lead time, monthly cost, batch temperature
X-bar and R (or S)Continuous, small subgroupsFive bottles weighed every hour
p chartDiscrete: proportion defectiveShare of invoices with errors each day
c or u chartDiscrete: count of defectsNumber of scratches per car or per square meter

Step 8 of 11Practice · Match the pairs

Match each situation to the most suitable control chart.

Tap an answer, then tap the place where it belongs (or drag it there).

  1. Weekly average lead time for loan approvals, one value per week
  2. Diameters of 4 pistons sampled every 30 minutes
  3. Percentage of late deliveries each day, with varying daily volumes
  4. Number of typing errors per 10-page document

Step 9 of 11Learn

The control plan

The control plan is the document that hands the improved process to its owner. It usually lists, for each critical step or CTQ:

  • What is measured (the process or output characteristic) and its target and limits.
  • How it's measured (method, gauge, operational definition).
  • How often and sample size.
  • Who measures and who reviews.
  • Where results are recorded (control chart, dashboard).
  • Reaction plan: exactly what to do when a signal appears, such as stop and quarantine, notify the supervisor, check the scanner, and escalate if not resolved within an hour.

Alongside the control plan, the team updates standard operating procedures and standard work, trains everyone involved (including future new hires through onboarding materials), and builds in visual management: boards and dashboards that show at a glance whether the process is on track.

Many organizations also hold short daily huddles at a visual board, where the team reviews yesterday's performance and today's issues in 10 to 15 minutes. These keep attention on the process long after the project team has moved on.

Finally, the team closes the project: confirms the results against the goal with data, documents lessons learned, validates financial benefits with finance, recognizes the people involved, and formally hands ownership to the process owner.

Step 10 of 11Practice · Select all that apply

Which elements belong in a good control plan? Select all that apply.

Select all that apply.

Step 11 of 11Practice · True or false

A process that is in statistical control will always meet customer specifications.