Demand Response, Transmission and the Smart Grid

See how flexible demand, smart meters, electric vehicles and long-distance transmission make a grid cheaper and more reliable.

Step 1 of 13Learn

Moving demand instead of supply

For a century, grids worked one way: demand did whatever it wanted, and power plants followed. A newer idea is to make demand flexible too. Demand response pays or rewards customers for using less electricity, or using it at a different time, when the grid is stressed.

Examples:

  • A utility sends a signal on a heat-wave afternoon, and thousands of smart thermostats raise their set point by 2 °F for two hours. Each home barely notices; together they cut hundreds of megawatts.
  • An aluminum smelter or data center agrees to reduce load on short notice in exchange for lower rates.
  • Water heaters heat up at midday when solar is plentiful and coast through the evening on stored hot water.

Time-of-use (TOU) pricing charges more per kWh during peak hours and less overnight or at midday. A typical design might charge three times more from 4–9 p.m. than at other times. Customers save money by running dishwashers, laundry and EV charging off-peak. Real-time pricing goes further, changing every hour or less with wholesale prices.

A cluster of flexible devices, such as home batteries, EV chargers, heat pumps and thermostats, coordinated by software to act like a single power plant is called a virtual power plant (VPP). Some VPPs already provide hundreds of megawatts of flexible capacity in the US, Australia and Europe.

The cheapest peak power plant is the one you never have to build.

Step 2 of 13Diagram

Anatomy of a demand response event

Anatomy of a demand response eventProcess diagram: Shortfall forecast → Signal sent → Loads adjust → Peak trimmed → Participants paid.Shortfall forecastSignal sentLoads adjustPeak trimmedParticipants paid

Tap a shape with to see more.

Shortfall forecast

The operator sees that demand will exceed available supply at the evening peak.

Signal sent

A price signal or event notice goes to aggregators, factories and smart devices.

Loads adjust

Thermostats shift, chargers pause, factories delay a process.

Peak trimmed

Demand falls by the needed megawatts without starting a peaker.

Participants paid

Customers earn credits or lower bills for their flexibility.

Step 3 of 13Try the calculator

Time-of-use savings

Shift some of your daily use from peak hours to off-peak hours and see the monthly difference.

Monthly cost before shifting
243 $
Monthly cost after shifting
189 $
Monthly savings
54 $

Step 4 of 13Practice · Work it out

Under time-of-use rates, peak power costs $0.40/kWh and off-peak power costs $0.12/kWh. If a household moves 6 kWh of daily EV charging from peak to off-peak, how much does it save over 30 days, in dollars?

Step 5 of 13Learn

Electric vehicles: a problem or a battery on wheels?

Electric vehicles add demand. A typical EV uses roughly 0.25–0.35 kWh per mile, so driving 12,000 miles a year adds about 3,000–4,000 kWh, about a third of an average US home's annual use. If millions of drivers plug in at 6 p.m. when they get home, they pile onto the evening peak.

But EVs are also flexible. A car is parked about 95% of the time and usually needs only a few hours of charging overnight. Managed charging, where the utility or the car's software schedules charging for cheap, low-demand hours, can absorb this load with little new capacity. Some programs shift charging to midday at workplaces, where it soaks up surplus solar.

Vehicle-to-grid (V2G) goes a step further: the car's battery sends power back to the home or grid during peaks. A typical EV battery of 60–80 kWh holds as much energy as several home batteries. A few school bus fleets and pilot programs already do this, and some newer EVs support bidirectional charging, though widespread V2G still faces cost and standards hurdles.

Heat pumps have a similar story: they shift heating from fuel to electricity and can raise winter peaks, but with good insulation and smart controls they can preheat homes before peak hours and coast through them.

Electrification of transport and heating could raise total electricity demand substantially by mid-century. How flexible that new demand is will strongly affect how much new generation and wiring we need.

Step 6 of 13Practice · What would you do?

What would you do?

A utility expects 200,000 new EVs in its area over five years. Planners worry that evening charging will require a new 300 MW gas peaker. What is the most cost-effective first step?

Step 7 of 13Practice · Chart

Evening plug-in vs managed EV charging

The same EVs need the same energy. Only the timing changes.

Tap the time when unmanaged charging adds the most load.

Tap the point that answers the question, then press Check.

Evening plug-in vs managed EV chargingLine chart with 8 categories: 15:00: Unmanaged 10 MW, Managed 5 MW; 17:00: Unmanaged 40 MW, Managed 10 MW; 19:00: Unmanaged 90 MW, Managed 15 MW; 21:00: Unmanaged 70 MW, Managed 25 MW; 23:00: Unmanaged 35 MW, Managed 50 MW; 1:00: Unmanaged 15 MW, Managed 55 MW; 3:00: Unmanaged 5 MW, Managed 55 MW; 5:00: Unmanaged 0 MW, Managed 50 MW.0 MW20 MW40 MW60 MW80 MW100 MW15:0017:0019:0021:0023:001:003:005:00Time
Illustrative load from 200,000 EVs; areas under the two curves are roughly equal.
Evening plug-in vs managed EV charging
TimeUnmanagedManaged
15:0010 MW5 MW
17:0040 MW10 MW
19:0090 MW15 MW
21:0070 MW25 MW
23:0035 MW50 MW
1:0015 MW55 MW
3:005 MW55 MW
5:000 MW50 MW

Step 8 of 13Learn

Transmission: the grid's bottleneck

Wind is strongest on the Great Plains and offshore; sunshine is strongest in deserts; demand is concentrated in cities. Transmission connects them. It also lets regions share reserves and smooth out local weather, so a calm day in one area can be covered by wind elsewhere.

Studies of US decarbonization pathways often find that transmission capacity would need to roughly double or more by mid-century. Yet building high-voltage lines is slow. A major interregional line can take 10 years or more to plan, permit and build, crossing many states, landowners and agencies. Meanwhile, hundreds of gigawatts of proposed solar, wind and storage projects wait in interconnection queues, the line of projects requesting permission to connect to the grid, often for several years.

Ways to get more out of the wires we already have, sometimes called grid-enhancing technologies, include:

  • Dynamic line ratings: sensors measure actual temperature and wind cooling a line, often allowing 10–30% more power than conservative fixed ratings.
  • Reconductoring: replacing old wires on existing towers with advanced conductors that carry up to about twice the power.
  • Advanced power flow control that routes power away from congested lines.

A smart grid combines these with digital communication: smart meters that report usage every 15 minutes, automated switches that isolate faults and reroute power, and software that coordinates millions of devices.

Step 9 of 13Practice · Select all that apply

Which are benefits of building more long-distance transmission? Select all that apply.

Select all that apply.

Step 10 of 13Practice · Choose one

A utility installs sensors that measure real-time wind and temperature on its lines and finds it can safely send more power through them on cool, windy days. What is this technology called?

Step 11 of 13Note

Step 12 of 13Diagram

The smart grid toolkit

The smart grid toolkitParts diagram: Smart grid, Smart meters, Virtual power plants, Dynamic line rating, Self-healing feeders, Time-varying rates.Smart gridSmart metersVirtual powerplantsDynamic lineratingSelf-healingfeedersTime-varyingrates

Tap a shape with to see more.

Smart grid
Smart meters

Measure use every 15 minutes or hourly, making time-varying prices possible.

Virtual power plants

Software that pools thousands of small devices and dispatches them like one plant.

Dynamic line rating

Lets lines carry more power when wind and cool air keep them cool.

Self-healing feeders

Automatic switches isolate a fault and reroute power around it in seconds.

Time-varying rates

Prices that reward using power when it is plentiful.

Step 13 of 13Practice · Sort into groups

Sort each measure: does it mainly shift when electricity is used, or reduce how much is used overall?

Tap an item, then tap its group (or drag it there).