Budgets and Earned Value

Build a project budget with contingency and management reserves, then measure cost and schedule performance with earned value: CV, SV, CPI, SPI and EAC.

Step 1 of 13Learn

Building the budget

A project budget is built the same way as a bottom-up estimate: cost each work package in the WBS, then roll the numbers up. Costs typically include:

  • Labor: hours × rate for each person or role. Usually the largest item on knowledge-work projects.
  • Materials and equipment: hardware, licenses, construction materials, rented equipment.
  • Services: contractors, consultants, venue hire.
  • Other: travel, training, permits, shipping.

Then come two layers of reserve, which are easy to confuse:

  • Contingency reserve: money set aside for identified risks ("known unknowns"). If your risk analysis says there's a real chance the vendor will raise prices, the contingency covers it. It's included in the cost baseline and typically managed by the project manager.
  • Management reserve: money held back for unforeseen work ("unknown unknowns"). It's not part of the cost baseline; using it usually requires management approval, and the baseline is adjusted when it is used.

So: work package estimates + contingency reserve = cost baseline; cost baseline + management reserve = total project budget. The total planned value of the work in the baseline is called the budget at completion (BAC).

The cost baseline is also time-phased: it shows how much is planned to be spent by each month. Plotted cumulatively, it forms an S-shaped curve (slow start, steep middle, slow finish), which becomes the yardstick for tracking performance.

Step 2 of 13Practice · Work it out

A project's work packages total $80,000. The team adds a contingency reserve of 10% for identified risks, and management holds a separate management reserve of $5,000. What is the cost baseline?

Step 3 of 13Practice · Diagram

How a project budget is stacked

Which layer is money for unknown unknowns that the project manager cannot spend without approval?

Tap the shape that answers the question, then press Check.

How a project budget is stackedPyramid diagram: Work package estimates, Contingency reserve, = Cost baseline, Management reserve, = Total project budget.Work package estimatesContingency reserve= Cost baselineManagementreserve= Total project budget
Work package estimates

Labor, materials, services and other costs rolled up from the WBS.

Contingency reserve

For identified risks ("known unknowns"). Part of the cost baseline; usually managed by the project manager.

= Cost baseline

The approved amount progress is measured against.

Management reserve

For unforeseen work ("unknown unknowns"). Outside the baseline; needs management approval to use.

= Total project budget

Step 4 of 13Learn

Why "percent spent" tells you almost nothing

Four months into a 10-month, $100,000 project, the finance report says $36,000 has been spent. Is that good or bad?

You can't tell. Maybe the plan called for $40,000 by now, so you're under budget. Or maybe only $30,000 worth of work is actually done, so you've paid $36,000 for $30,000 of results. Spending alone mixes up two questions: are we on schedule? and are we getting the work we're paying for?

Earned value management (EVM) answers both by comparing three numbers at any point in time:

  • Planned value (PV): the budgeted cost of the work that should be done by now, according to the baseline. Here, the plan said 40% of the work by month 4: PV = $40,000.
  • Earned value (EV): the budgeted cost of the work that is actually done. The team has completed 30% of the work: EV = 30% × $100,000 = $30,000.
  • Actual cost (AC): what has really been spent to get that work done: AC = $36,000.

The key idea is EV: it measures progress in budget dollars, so it can be compared directly with both the plan (PV) and the spending (AC). It is only as good as the measurement of "percent complete", so teams often use objective rules, such as counting a work package as 0% until started, 50% once started and 100% only when finished.

Step 5 of 13Chart

PV, EV and AC over the first four months

The planned line (PV) is above the earned line (EV): behind schedule. The actual cost line (AC) is above EV: paying more than the work is worth.

PV, EV and AC over the first four monthsLine chart with 5 categories: Month 0: Planned value (PV) $0, Earned value (EV) $0, Actual cost (AC) $0; Month 1: Planned value (PV) $8,000, Earned value (EV) $6,000, Actual cost (AC) $7,000; Month 2: Planned value (PV) $18,000, Earned value (EV) $14,000, Actual cost (AC) $16,000; Month 3: Planned value (PV) $29,000, Earned value (EV) $22,000, Actual cost (AC) $26,000; Month 4: Planned value (PV) $40,000, Earned value (EV) $30,000, Actual cost (AC) $36,000.$0$10k$20k$30k$40kMonth 0Month 1Month 2Month 3Month 4$40,000$30,000$36,000
Illustrative monthly path matching the lesson example ($100,000 project, month 4: PV $40,000, EV $30,000, AC $36,000).
PV, EV and AC over the first four months
ItemPlanned value (PV)Earned value (EV)Actual cost (AC)
Month 0$0$0$0
Month 1$8,000$6,000$7,000
Month 2$18,000$14,000$16,000
Month 3$29,000$22,000$26,000
Month 4$40,000$30,000$36,000

Step 6 of 13Learn

Variances, indices and forecasts

With PV, EV and AC you can calculate everything that matters. Using the example (PV $40,000, EV $30,000, AC $36,000, BAC $100,000):

MeasureFormulaExampleMeaning
Cost variance (CV)EV − AC−$6,000over budget for the work done
Schedule variance (SV)EV − PV−$10,000behind schedule (in budget terms)
Cost performance index (CPI)EV / AC0.83earning 83 cents of work per dollar
Schedule performance index (SPI)EV / PV0.75progressing at 75% of the planned rate
Estimate at completion (EAC)BAC / CPI$120,000forecast final cost if efficiency continues
Variance at completion (VAC)BAC − EAC−$20,000expected overrun

The pattern is easy to remember: every formula starts with EV. Variances subtract, indices divide. Negative variances and indices below 1 are bad; positive variances and indices above 1 are good.

The EAC is the headline number for sponsors. With a CPI of 0.83 four months in, the project is heading for about $120,000, not $100,000. Research on large projects has found that CPI tends to be fairly stable once a project is 15% to 20% complete, so an early poor CPI is a serious warning, not a blip.

SV and SPI measure schedule in money, not days, and at the very end of a project SV always returns to zero (all work is earned), so use them together with the critical path for schedule decisions.

Step 7 of 13Try the calculator

Earned value calculator

Enter the budget and the three earned value measures to get the variances, indices and forecast.

Cost variance CV = EV − AC
-6,000 $
Schedule variance SV = EV − PV
-10,000 $
CPI = EV / AC
0.83
SPI = EV / PV
0.75
EAC = BAC / CPI
120,000 $
VAC = BAC − EAC
-20,000 $

Step 8 of 13Practice · Work it out

A project has earned value of $45,000 and actual cost of $50,000. What is the CPI? Give two decimal places.

Step 9 of 13Practice · Choose one

A project reports SPI = 1.10 and CPI = 0.80. What does this mean?

Step 10 of 13Practice · Diagram

Reading SPI and CPI together

A project reports SPI 0.90 and CPI 1.15. Which corner is it in?

Tap the shape that answers the question, then press Check.

Reading SPI and CPI togetherTwo-by-two matrix: Behind, under budget, Ahead, under budget, Behind, over budget, Ahead, over budget.Behind, under budgetAhead, under budgetBehind, over budgetAhead, over budgetSchedule (SPI)Below 1: behindAbove 1: aheadCost (CPI)Below 1: over budgetAbove 1: under budget
Behind, under budget

Often a resourcing problem: people not yet assigned, so little is spent and little is done.

Ahead, under budget

Everything going well. Check the measurements are honest.

Behind, over budget

The worst corner: escalate with a forecast and recovery options.

Ahead, over budget

Speed is being bought, for example with overtime or contractors.

Step 11 of 13Note

Step 12 of 13Practice · Work it out

A project has a budget at completion of $200,000 and a CPI of 0.80. If cost performance continues at the same rate, what is the estimate at completion (EAC)?

Step 13 of 13Practice · Fill in the blanks

Fill in the blanks

Cost variance is EV minus , and schedule variance is EV minus .