Module 1: Project BasicsLesson 1 of 1211 min

What Is a Project?

Tell projects apart from routine operations, understand the triple constraint and quality, meet the key roles, and see why projects most often fail.

Step 1 of 13Learn

Projects versus everyday work

Priya works in finance. Every month she runs payroll for 400 employees: same steps, same deadline, month after month. In March her boss asks her to move the department to a new payroll system by September. Both jobs involve payroll, but they are very different kinds of work.

Running payroll is operations: ongoing, repetitive work that keeps the organization running. Moving to a new system is a project: a temporary effort, with a defined start and end, undertaken to create a unique product, service or result.

Those two words do the work in the definition:

  • Temporary means the project ends, either when its objectives are achieved or when it's stopped because they can't or shouldn't be. Temporary doesn't mean short; building a hospital can take years. The result may last for decades.
  • Unique means something new is created. Even if you've moved offices before, this move, with this building, these people and this budget, has never happened exactly like this.

Projects exist to create change: a new product, a new process, a new building, a new capability. Once a project delivers, its result usually passes into operations. Priya's new payroll system will be run month after month by the operations team.

Why does the distinction matter? Because projects need things routine work doesn't: a clear goal and end point, a plan built from scratch, a temporary team, and someone responsible for pulling it all together, the project manager.

Step 2 of 13Practice · Sort into groups

Sort each piece of work as a project or operations.

Tap an item, then tap its group (or drag it there).

Step 3 of 13Compare

Project or operations?

AspectProjectOperations
DurationTemporary: has a planned start and endOngoing: continues indefinitely
OutputSomething unique (new system, building, event)The same product or service, repeatedly
TeamAssembled for the project, then releasedStable department
GoalCreate change, then stopKeep the business running smoothly
Payroll exampleMove to a new payroll system by SeptemberRun payroll for 400 people every month

Step 4 of 13Learn

The triple constraint, and quality

Every project is squeezed by three linked limits, often drawn as a triangle:

  • Scope: what will be delivered, and how much work that takes.
  • Time: the schedule and deadline.
  • Cost: the budget, including people, materials and tools.

Change one side and at least one other must move. Suppose a website redesign is planned for 12 weeks and $60,000. The client now wants it in 8 weeks. The project manager has real options, each with a price:

  • Cut scope: launch with the core pages and add the blog later.
  • Raise cost: add two developers or pay for overtime, if the work can be split.
  • Accept risk to quality: skip testing. This is the option teams fall into when nobody makes a deliberate choice, and it usually costs more later.

Quality sits in the middle of the triangle: squeezing any side without adjusting another puts quality at risk. Modern guidance often speaks of competing constraints more broadly, adding risk, resources and stakeholder satisfaction, but the core lesson is the same: you can't change one constraint for free.

A useful early question for any sponsor is "Which of the three is most fixed?" A wedding date is fixed, so scope and cost must flex. A grant has a fixed budget. A regulatory requirement fixes scope. Knowing which side is rigid tells you where you have room to maneuver.

The triple constraint triangle with scope, time and cost at the corners and quality in the middleScopeTimeCostQuality

Step 5 of 13Practice · What would you do?

What would you do?

A product launch is planned for June 30 with a budget of $200,000 and 12 features. In March the sponsor announces the launch must move to May 31 for a trade show, and no extra money is available. What should the project manager do first?

Step 6 of 13Learn

Who is involved

A project is a temporary organization with roles that matter more than job titles:

  • Sponsor: the senior person who wants the project, provides funding and authority, and makes the big decisions. A project without an engaged sponsor is in danger from day one.
  • Project manager: the person accountable for delivering the project's objectives. They plan, coordinate, track, remove obstacles and, above all, communicate. They rarely do the specialist work themselves.
  • Project team: the people who do the work, often borrowed part-time from different departments.
  • Functional managers: the bosses who "lend" team members and control their other priorities.
  • Customers and users: the people who will receive or use the result. They may be internal or external.
  • Other stakeholders: anyone who affects or is affected by the project, from regulators to the IT security team to the neighbors of a construction site.

The project manager's job is often described as integration: making sure the plan, the people and the pieces fit together. Much of that is communication: understanding what each stakeholder needs, translating between technical teams and executives, and making sure decisions are made and recorded.

In many organizations, project managers have limited formal authority over team members. They lead by influence: clear goals, good plans, credibility and relationships.

Step 7 of 13Practice · Match the pairs

Match each project role to its description.

Tap an answer, then tap the place where it belongs (or drag it there).

  1. Sponsor
  2. Project manager
  3. Project team
  4. Functional manager
  5. End users

Step 8 of 13Diagram

Who sits around a project

Tap each role to see what it contributes. Lines show the usual line of authority and support, not job seniority.

Who sits around a projectHierarchy diagram: Sponsor, Project manager, Functional managers, Project team, Customers and users, Other stakeholders.SponsorProjectmanagerFunctionalmanagersProject teamCustomers andusersOtherstakeholders

Tap a shape with to see more.

Sponsor

Funds the project, owns the business case and makes the big decisions.

Project manager

Accountable for delivery: plans, coordinates, tracks and communicates.

Functional managers

Lend people to the project and control their other priorities.

Project team

Does the specialist work, often part-time and borrowed from several departments.

Customers and users

Receive or use the result; their needs define success.

Other stakeholders

Regulators, IT security, neighbors: anyone affected or able to affect the project.

Step 9 of 13Learn

Why projects fail, and what success means

Project post-mortems keep finding the same causes of failure:

  1. Unclear objectives: the team builds something, but nobody agreed exactly what "done" looks like.
  2. Scope creep: small additions pile up without anyone adjusting time or budget.
  3. Unrealistic estimates: deadlines set by wishful thinking or by a date someone promised a customer.
  4. Weak sponsorship: no one senior enough to make decisions, secure resources or resolve conflicts.
  5. Poor communication: stakeholders are surprised, team members work on outdated information.
  6. Ignored risks: problems that were foreseeable but nobody planned for.

Notice that almost all of these are decided early, in the way a project is defined and planned. That's why the first modules of this course focus on charters, scope and planning.

What does success look like? The traditional answer is "on time, on budget, in scope, at the agreed quality". A more complete answer adds: the project delivered the benefits it was meant to. A customer portal delivered perfectly on schedule is still a failure if customers don't use it. Good project managers keep asking why the project exists, not just what it must produce.

Step 10 of 13Note

Step 11 of 13Practice · Diagram

From what a project delivers to why it was funded

Which item may only become measurable months after the project has closed?

Tap the shape that answers the question, then press Check.

From what a project delivers to why it was fundedProcess diagram: Output: new website → Outcome: customers order online → Benefit: 20% more repeat orders.Output: new websiteOutcome: customersorder onlineBenefit: 20% morerepeat orders
Output: new website

What the project hands over. Projects are usually judged here.

Outcome: customers order online

The change the output makes possible once people use it.

Benefit: 20% more repeat orders

The measurable gain the organization paid for. It often appears after the project has closed.

Step 12 of 13Practice · True or false

A project officially ends when its budget is used up.

Step 13 of 13Practice · Choose one

Which of these is the best example of a project?