Module 3: Schedule and BudgetLesson 6 of 1214 min

Scheduling and the Critical Path

Sequence activities with dependencies, find the critical path and float, read a Gantt chart, and shorten a schedule by crashing or fast-tracking.

Step 1 of 12Learn

Activities and dependencies

Work packages are broken into activities: the actions that appear in a schedule, such as "write the speaker brief" or "install the projector". To build a schedule, you need each activity's duration and its dependencies, meaning which activities must happen before others.

There are four types of dependency between a predecessor and a successor:

  • Finish-to-start (FS): the successor can't start until the predecessor finishes. Pour the concrete, then build the walls. By far the most common.
  • Start-to-start (SS): the successor can't start until the predecessor starts. Once writing has started, editing can start.
  • Finish-to-finish (FF): the successor can't finish until the predecessor finishes. Testing can't finish until development finishes.
  • Start-to-finish (SF): the successor can't finish until the predecessor starts. The night shift can't end until the morning shift starts. Rare.

Dependencies can have a lag (a required wait): paint must dry for 2 days before the second coat, so the FS link has a 2-day lag. A lead lets a successor start before its predecessor finishes: begin writing the user guide 5 days before development ends.

Dependencies also have causes. Some are mandatory (physics or law: you can't test what isn't built), some are discretionary (best practice or preference) and some are external (a supplier delivery, a permit). Knowing which is which matters later: discretionary dependencies are the ones you can relax to save time.

Step 2 of 12Practice · Match the pairs

Match each dependency type to an example.

Tap an answer, then tap the place where it belongs (or drag it there).

  1. Finish-to-start
  2. Start-to-start
  3. Finish-to-finish
  4. Start-to-finish
  5. Lag

Step 3 of 12Learn

The critical path

Lay activities out as boxes connected by arrows and you get a network diagram. Consider a small website launch:

ActivityDurationDepends on
A Plan content3 daysnone
B Build site5 daysA
C Write copy2 daysA
D Launch2 daysB and C

There are two paths from start to finish:

  • A → B → D: 3 + 5 + 2 = 10 days
  • A → C → D: 3 + 2 + 2 = 7 days

D can't start until both B and C are done, so the project takes as long as the longest path: 10 days. That longest path, A → B → D, is the critical path. Any delay to an activity on it delays the whole project day for day.

Activity C isn't critical. It has float (also called slack): it can slip by 10 − 7 = 3 days without delaying the launch. If copywriting takes 4 days instead of 2, the project still finishes on day 10. If it takes 6, C's path becomes 11 days and the critical path changes.

Two lessons follow. First, focus attention on critical activities, because that's where delays hurt. Second, the critical path isn't always the "most important" work; it's simply the longest chain of dependent work, and it can shift as actual durations replace estimates.

Network diagram: A (3 days) leads to B (5 days) and C (2 days), both lead to D (2 days); the critical path A, B, D is highlightedA 3dB 5dC 2dD 2d

Step 4 of 12Practice · Work it out

In the website example, suppose writing the copy (C) actually takes 6 days instead of 2, and every other activity stays the same. How many days does the project now take?

Step 5 of 12Learn

Forward pass, backward pass and float

For larger networks, project managers calculate four dates for each activity:

  • Early start (ES) and early finish (EF): the earliest the activity can start and finish, found by a forward pass from the start. EF = ES + duration, and an activity's ES is the latest EF among its predecessors.
  • Late start (LS) and late finish (LF): the latest it can start and finish without delaying the project, found by a backward pass from the end. LS = LF − duration, and an activity's LF is the earliest LS among its successors.

Total float = LS − ES (or LF − EF). Activities with zero float form the critical path.

In the website example, using "day 0" as the start: A runs 0 to 3; B runs 3 to 8; C can run 3 to 5 at the earliest; D runs 8 to 10. Working backward from day 10, D must start by day 8, so C must finish by day 8 and start by day 6. C's float is 6 − 3 = 3 days, as we found by comparing paths.

Scheduling software does these calculations instantly, but understanding them lets you sanity-check the tool and answer questions like "if the supplier is a week late, does it matter?" (Only if that activity's float is less than a week.)

Watch out for near-critical paths: a path with only one or two days of float can become critical with a small slip, so it deserves almost as much attention as the critical path itself.

Step 6 of 12Practice · Chart

Website launch as a simple Gantt view

Each bar waits until its early start, then shows the work. A, B and D chain end to end; C finishes early and has room to slip.

Which activity is the only one with float?

Tap the bar that answers the question, then press Check.

Website launch as a simple Gantt viewStacked bar chart with 4 categories: A Plan content: Waiting before early start 0, Work (days) 3; B Build site: Waiting before early start 3, Work (days) 5; C Write copy: Waiting before early start 3, Work (days) 2; D Launch: Waiting before early start 8, Work (days) 2.0246810DayA Plan contentB Build siteC Write copyD Launch38510
Website launch as a simple Gantt view
ItemWaiting before early startWork (days)
A Plan content03
B Build site35
C Write copy32
D Launch82

Step 7 of 12Practice · Work it out

A project has these activities: A (4 days, no predecessor), B (3 days, no predecessor), C (6 days, after A), D (5 days, after B) and E (2 days, after both C and D). What is the shortest possible project duration?

Step 8 of 12Learn

Gantt charts, milestones and compressing a schedule

A Gantt chart shows activities as horizontal bars against a calendar, often with arrows for dependencies and the critical path highlighted. It's the most common way to communicate a schedule because anyone can read it at a glance. Milestones, such as "contract signed" or "go-live", are zero-duration markers, usually shown as diamonds. Once approved, the schedule becomes the schedule baseline, and progress is compared against it.

When the schedule is too long, there are two main compression techniques, and both only help if applied to critical path activities:

  • Crashing: add resources to shorten an activity, such as extra staff, overtime or faster equipment. It costs more money. Crash the activities that give the most time saved per dollar first, and remember that some work doesn't speed up with more people: adding programmers to a late software project can make it later, because new people need onboarding and coordination.
  • Fast-tracking: do activities in parallel that were planned in sequence, such as starting construction before the design is fully finished. It adds risk, mainly of rework if earlier decisions change. It works only where dependencies are discretionary, not mandatory.

Shortening a non-critical activity saves nothing, because the critical path still sets the end date. And compression can shift the critical path: once one path is shortened, another may become the longest.

Step 9 of 12Practice · What would you do?

What would you do?

A product launch is 2 weeks behind schedule. The critical path includes "Build marketing website" (4 weeks, one developer). The non-critical activity "Print brochures" has 3 weeks of float. The sponsor will approve a modest budget increase. What is the best first move?

Step 10 of 12Practice · True or false

Shortening any activity in a project, whether or not it is on the critical path, will shorten the overall project duration.

Step 11 of 12Compare

Two ways to compress a schedule

AspectCrashingFast-tracking
What you doAdd resources: people, overtime, faster equipmentOverlap activities that were planned in sequence
Main costMore moneyMore risk and possible rework
Works best whenThe work can genuinely be splitLater work can start on partial information
ExampleHire a contractor to help build the siteStart design before all requirements are signed off
Apply toCritical path activities onlyCritical path activities only

Step 12 of 12Practice · Choose one

Which statement best describes the critical path?