Scheduling and the Critical Path
Sequence activities with dependencies, find the critical path and float, read a Gantt chart, and shorten a schedule by crashing or fast-tracking.
Welcome back!
Step 1 of 12Learn
Activities and dependencies
Work packages are broken into activities: the actions that appear in a schedule, such as "write the speaker brief" or "install the projector". To build a schedule, you need each activity's duration and its dependencies, meaning which activities must happen before others.
There are four types of dependency between a predecessor and a successor:
- Finish-to-start (FS): the successor can't start until the predecessor finishes. Pour the concrete, then build the walls. By far the most common.
- Start-to-start (SS): the successor can't start until the predecessor starts. Once writing has started, editing can start.
- Finish-to-finish (FF): the successor can't finish until the predecessor finishes. Testing can't finish until development finishes.
- Start-to-finish (SF): the successor can't finish until the predecessor starts. The night shift can't end until the morning shift starts. Rare.
Dependencies can have a lag (a required wait): paint must dry for 2 days before the second coat, so the FS link has a 2-day lag. A lead lets a successor start before its predecessor finishes: begin writing the user guide 5 days before development ends.
Dependencies also have causes. Some are mandatory (physics or law: you can't test what isn't built), some are discretionary (best practice or preference) and some are external (a supplier delivery, a permit). Knowing which is which matters later: discretionary dependencies are the ones you can relax to save time.
Step 2 of 12Practice · Match the pairs
Match each dependency type to an example.
Tap an answer, then tap the place where it belongs (or drag it there).
- Finish-to-start
- Start-to-start
- Finish-to-finish
- Start-to-finish
- Lag
Step 3 of 12Learn
The critical path
Lay activities out as boxes connected by arrows and you get a network diagram. Consider a small website launch:
| Activity | Duration | Depends on |
|---|---|---|
| A Plan content | 3 days | none |
| B Build site | 5 days | A |
| C Write copy | 2 days | A |
| D Launch | 2 days | B and C |
There are two paths from start to finish:
- A → B → D: 3 + 5 + 2 = 10 days
- A → C → D: 3 + 2 + 2 = 7 days
D can't start until both B and C are done, so the project takes as long as the longest path: 10 days. That longest path, A → B → D, is the critical path. Any delay to an activity on it delays the whole project day for day.
Activity C isn't critical. It has float (also called slack): it can slip by 10 − 7 = 3 days without delaying the launch. If copywriting takes 4 days instead of 2, the project still finishes on day 10. If it takes 6, C's path becomes 11 days and the critical path changes.
Two lessons follow. First, focus attention on critical activities, because that's where delays hurt. Second, the critical path isn't always the "most important" work; it's simply the longest chain of dependent work, and it can shift as actual durations replace estimates.
Step 4 of 12Practice · Work it out
In the website example, suppose writing the copy (C) actually takes 6 days instead of 2, and every other activity stays the same. How many days does the project now take?
Step 5 of 12Learn
Forward pass, backward pass and float
For larger networks, project managers calculate four dates for each activity:
- Early start (ES) and early finish (EF): the earliest the activity can start and finish, found by a forward pass from the start. EF = ES + duration, and an activity's ES is the latest EF among its predecessors.
- Late start (LS) and late finish (LF): the latest it can start and finish without delaying the project, found by a backward pass from the end. LS = LF − duration, and an activity's LF is the earliest LS among its successors.
Total float = LS − ES (or LF − EF). Activities with zero float form the critical path.
In the website example, using "day 0" as the start: A runs 0 to 3; B runs 3 to 8; C can run 3 to 5 at the earliest; D runs 8 to 10. Working backward from day 10, D must start by day 8, so C must finish by day 8 and start by day 6. C's float is 6 − 3 = 3 days, as we found by comparing paths.
Scheduling software does these calculations instantly, but understanding them lets you sanity-check the tool and answer questions like "if the supplier is a week late, does it matter?" (Only if that activity's float is less than a week.)
Watch out for near-critical paths: a path with only one or two days of float can become critical with a small slip, so it deserves almost as much attention as the critical path itself.
Step 6 of 12Practice · Chart
Website launch as a simple Gantt view
Each bar waits until its early start, then shows the work. A, B and D chain end to end; C finishes early and has room to slip.
Which activity is the only one with float?
Tap the bar that answers the question, then press Check.
| Item | Waiting before early start | Work (days) |
|---|---|---|
| A Plan content | 0 | 3 |
| B Build site | 3 | 5 |
| C Write copy | 3 | 2 |
| D Launch | 8 | 2 |
Step 7 of 12Practice · Work it out
A project has these activities: A (4 days, no predecessor), B (3 days, no predecessor), C (6 days, after A), D (5 days, after B) and E (2 days, after both C and D). What is the shortest possible project duration?
Step 8 of 12Learn
Gantt charts, milestones and compressing a schedule
A Gantt chart shows activities as horizontal bars against a calendar, often with arrows for dependencies and the critical path highlighted. It's the most common way to communicate a schedule because anyone can read it at a glance. Milestones, such as "contract signed" or "go-live", are zero-duration markers, usually shown as diamonds. Once approved, the schedule becomes the schedule baseline, and progress is compared against it.
When the schedule is too long, there are two main compression techniques, and both only help if applied to critical path activities:
- Crashing: add resources to shorten an activity, such as extra staff, overtime or faster equipment. It costs more money. Crash the activities that give the most time saved per dollar first, and remember that some work doesn't speed up with more people: adding programmers to a late software project can make it later, because new people need onboarding and coordination.
- Fast-tracking: do activities in parallel that were planned in sequence, such as starting construction before the design is fully finished. It adds risk, mainly of rework if earlier decisions change. It works only where dependencies are discretionary, not mandatory.
Shortening a non-critical activity saves nothing, because the critical path still sets the end date. And compression can shift the critical path: once one path is shortened, another may become the longest.
Step 9 of 12Practice · What would you do?
What would you do?
A product launch is 2 weeks behind schedule. The critical path includes "Build marketing website" (4 weeks, one developer). The non-critical activity "Print brochures" has 3 weeks of float. The sponsor will approve a modest budget increase. What is the best first move?
Step 10 of 12Practice · True or false
Shortening any activity in a project, whether or not it is on the critical path, will shorten the overall project duration.
Step 11 of 12Compare
Two ways to compress a schedule
| Aspect | Crashing | Fast-tracking |
|---|---|---|
| What you do | Add resources: people, overtime, faster equipment | Overlap activities that were planned in sequence |
| Main cost | More money | More risk and possible rework |
| Works best when | The work can genuinely be split | Later work can start on partial information |
| Example | Hire a contractor to help build the site | Start design before all requirements are signed off |
| Apply to | Critical path activities only | Critical path activities only |
Step 12 of 12Practice · Choose one
Which statement best describes the critical path?