Quality and Change Control
Plan and control quality, understand the cost of quality, run a clear change control process, and keep issue, change and decision logs.
Welcome back!
Step 1 of 14Learn
What quality means on a project
A project can finish on time and on budget and still fail if what it delivers doesn't work. Quality, in project terms, means the degree to which the deliverables meet requirements and are fit for their intended use. A mobile app that crashes when 500 people log in at once doesn't meet the requirement to support launch-day traffic, however beautiful it looks.
Don't confuse quality with grade. Grade is a category of features or materials: a budget hotel and a luxury hotel are different grades. A budget hotel with clean rooms and working showers is high quality, low grade. A luxury hotel with broken air conditioning is high grade, low quality. Low grade may be perfectly acceptable; low quality never is.
Modern quality management rests on one principle: prevention over inspection. It's cheaper to build quality in than to find defects at the end. That's captured in the cost of quality:
- Cost of conformance (money spent to get it right): prevention costs such as training, standards, design reviews; and appraisal costs such as testing and inspections.
- Cost of nonconformance (money lost because it wasn't right): internal failure costs such as rework and scrap found before delivery; and external failure costs such as warranty claims, recalls, support calls and lost customers.
A defect caught in a design review might cost an hour. The same defect found by a customer after launch can cost thousands, plus reputation.
Step 2 of 14Practice · Sort into groups
Sort each cost into cost of conformance or cost of nonconformance.
Tap an item, then tap its group (or drag it there).
Step 3 of 14Practice · Chart
The later a defect is found, the more it costs to fix
Tap the stage where fixing a defect is cheapest.
Tap the bar that answers the question, then press Check.
Step 4 of 14Learn
Planning and controlling quality
Quality starts in planning, with clear, testable acceptance criteria for every deliverable. "The report is easy to read" can't be checked; "the monthly report fits on two pages and is approved by the finance director" can. Agile teams use a shared definition of done: a checklist every piece of work must meet, such as code reviewed, tests passed and documentation updated.
Two related activities are often confused:
- Quality assurance (management) is about the process: are we working in a way that produces quality? Audits, standards, process improvements, checklists, training.
- Quality control is about the product: does this deliverable meet its requirements? Inspections, testing, reviews and measurements.
When defects appear, look for root causes rather than blaming people:
- The 5 whys: keep asking "why?" until you reach a cause you can fix. The invoice was wrong. Why? The tax rate was outdated. Why? Rates are typed by hand. Why? There is no shared rate table. Fix: a shared, maintained rate table.
- Pareto analysis: count defects by cause and sort them. Often a few causes (roughly 20%) produce most of the problems (roughly 80%), so fixing those first gives the biggest improvement.
- Cause-and-effect (fishbone) diagrams group possible causes under headings such as people, process, tools and materials.
Quality is everyone's job, but the project manager makes sure it's planned, measured and not quietly squeezed out when the schedule gets tight.
Step 5 of 14Compare
Quality assurance vs quality control
| Aspect | Quality assurance | Quality control |
|---|---|---|
| Focus | The process | The product |
| Question | Are we working in a way that produces quality? | Does this deliverable meet its requirements? |
| Activities | Audits, standards, checklists, training | Inspections, tests, reviews, measurements |
| Timing | Before and during the work | On finished pieces of work |
Step 6 of 14Practice · True or false
A low-grade product, such as a basic budget model, is by definition a low-quality product.
Step 7 of 14Diagram
Quality and grade are different things
Tap a shape with to see more.
- Budget hotel, clean and working
Low grade, high quality: perfectly acceptable.
- Luxury hotel, flawless
High grade, high quality.
- Budget hotel, broken shower
Low grade, low quality: a failure.
- Luxury hotel, broken AC
High grade, low quality: an expensive failure.
Step 8 of 14Learn
Controlling changes
Changes are normal. Markets move, users learn what they want, regulations shift. What causes damage is uncontrolled change: requests slipped in through hallway conversations, approved by whoever happened to be asked, with no adjustment to schedule or budget.
A change control process keeps changes deliberate:
- Submit a change request describing the change and why it's needed.
- Log it in the change log so nothing gets lost.
- Analyze the impact on scope, schedule, cost, quality, risk and resources.
- Decide: the sponsor or a change control board (CCB) approves, rejects or defers it, according to authority levels agreed at the start (for example, the project manager may approve changes under $2,000 and one day of delay).
- Update the baselines and plans if approved.
- Communicate the decision to everyone affected, and implement it.
The process should be proportionate. A small internal project might need a one-page form and a weekly 15-minute review; a large construction contract might need formal boards and contract amendments.
Agile projects handle change differently but not loosely: new requests go into the product backlog, where the product owner prioritizes them against everything else. The time box stays fixed, so adding one item means something else moves down the list, which makes the trade-off just as visible.
Step 9 of 14Practice · Put in order
Put the steps of a change control process in order.
Drag the items, or use the arrow buttons, to put them in order.
- Analyze the impact on scope, schedule, cost, quality and risk
- Record it in the change log
- Approve, reject or defer it at the right level of authority
- Submit a change request
- Update the baselines and communicate the decision
Step 10 of 14Practice · Diagram
The change control process
At which step does a change control board do its main job?
Tap the shape that answers the question, then press Check.
- Submit request
- Log it
- Analyze impact
Scope, schedule, cost, quality, risk and resources.
- Decide
Sponsor or change control board, within agreed authority levels.
- Update baselines
- Communicate and implement
Step 11 of 14Learn
The project manager's logs
Projects generate many small facts that become critical later: who decided what, which problems are open, which changes were approved. A few simple logs keep that memory outside anyone's head:
- Risk register: possible future events, their scores, owners and responses.
- Issue log: current problems, their impact, owner, actions and target dates. An issue without an owner and a date tends to stay open forever.
- Change log: every change request, its impact assessment and decision.
- Decision log: important decisions, who made them, when and why. Six months later, when someone asks "why did we choose this vendor?", the answer is there.
- Lessons learned register: what went well and what didn't, recorded during the project, not just at the end.
These can be tabs in one shared spreadsheet or features in a project tool. What matters is that they are current, visible and used: reviewed in team meetings, referenced in status reports and updated as things change.
A useful mental model is the life cycle between them: a risk that materializes becomes an issue; resolving an issue may require a change request; approving the change is a decision; and the whole episode becomes a lesson learned. Keeping the logs linked tells the story of the project.
Step 12 of 14Practice · Match the pairs
Match each log to what it records.
Tap an answer, then tap the place where it belongs (or drag it there).
- Risk register
- Issue log
- Change log
- Decision log
- Lessons learned register
Step 13 of 14Practice · What would you do?
What would you do?
During a client meeting, the client's marketing manager verbally asks the lead developer to change the checkout flow. The developer agrees and starts work that afternoon. The project manager hears about it a week later. What should happen now?
Step 14 of 14Practice · Choose one
What does the quality principle "prevention over inspection" mean in practice?