Life Cycles and Methodologies
Walk through the five project process groups, compare predictive, Agile and hybrid approaches, and choose the right one for a given project.
Welcome back!
Step 1 of 13Learn
From idea to closure
A bridge and a mobile app look nothing alike, yet both projects pass through recognizable stages. A widely used way of organizing project work divides it into five process groups:
- Initiating: define the project at a high level, confirm it's worth doing and get formal authorization, usually with a project charter.
- Planning: work out scope, schedule, budget, risks, communication and quality, in as much detail as the approach requires.
- Executing: do the work, coordinate people and produce the deliverables.
- Monitoring and controlling: measure progress against the plan, manage changes and correct course. This runs alongside execution, not after it.
- Closing: get formal acceptance, hand over the result, release the team, and capture lessons learned.
Here's how it looked for Malik's warehouse relocation: the COO approved a one-page charter (initiating); Malik's team built a schedule, budget and moving plan (planning); movers and IT crews did the work over three weekends (executing); Malik tracked progress daily and handled a delayed forklift delivery (monitoring and controlling); and the team signed off with the warehouse manager and recorded what they'd do differently next time (closing).
These groups aren't strictly one-time phases. On a long project you may plan, execute and monitor many times, phase by phase. But every project, however small, needs all five.
Step 2 of 13Practice · Put in order
Put the five project process groups in their usual order.
Drag the items, or use the arrow buttons, to put them in order.
- Executing
- Closing
- Planning
- Initiating
- Monitoring and controlling
Step 3 of 13Practice · Diagram
The five process groups in Malik's warehouse move
Which process group does not wait its turn but runs at the same time as executing?
Tap the shape that answers the question, then press Check.
- Initiating
The COO approved a one-page charter.
- Planning
Schedule, budget and moving plan.
- Executing
Movers and IT crews worked over three weekends.
- Monitoring and controlling
Daily tracking; handling the late forklift delivery. Runs alongside executing.
- Closing
Acceptance, handover, releasing the team, lessons learned.
Step 4 of 13Learn
Predictive (waterfall) projects
In a predictive approach, often called waterfall, the team defines scope, schedule and cost as completely as possible up front, then works through phases in sequence: requirements, design, build, test, deploy. Each phase finishes, often with a formal review or phase gate, before the next begins.
Predictive planning works well when:
- The requirements are clear and stable: a bridge's span and load don't change halfway through.
- Changes late in the work are very expensive: you can't easily move a foundation after the walls are up.
- Contracts, regulations or safety demand detailed documentation and approvals.
- The team has done similar work before, so estimates are reliable.
Its strengths are predictability and clarity: everyone knows the plan, the budget and the delivery date, and progress is easy to compare against a baseline.
Its weakness appears when requirements are uncertain. Users often don't know what they want until they see something working. In a pure waterfall project they might not see anything until testing, months in, when changes are most expensive. A software system that perfectly matches a two-year-old specification can still miss what the business needs today.
Step 5 of 13Diagram
A predictive (waterfall) sequence
Each phase finishes, often with a phase-gate review, before the next one starts.
Tap a shape with to see more.
- Requirements
Agree what must be built, in detail.
- Design
Decide how it will be built.
- Build
Construct or code the deliverables.
- Test
Check the result against the requirements. Often the first time users see it working.
- Deploy
Hand it over and go live.
Step 6 of 13Learn
Agile and hybrid approaches
Agile approaches deliver work in small increments over short cycles, often two to four weeks, called iterations or sprints. Each cycle produces something usable that stakeholders can review. Their feedback shapes the next cycle. Instead of fixing scope at the start and letting time and cost float, Agile teams typically fix time and cost per cycle and let the scope adapt, delivering the most valuable features first.
Agile works well when:
- Requirements are uncertain or likely to change, as with new products and digital services.
- Early feedback is valuable, and partial delivery is useful (a first version of an app can go live).
- The team can work closely with users or a product owner who makes priority decisions.
The ideas behind Agile were summarized in the Manifesto for Agile Software Development (2001), which values individuals and interactions, working software, customer collaboration and responding to change. Popular frameworks include Scrum and Kanban, covered in Module 5.
Many real projects are hybrid. A hospital building may use a predictive plan for construction and Agile sprints for its patient app. A product team may set fixed annual milestones but work in sprints between them. The question is never "which method is best?" but "which approach fits this work, these stakeholders and this level of uncertainty?"
Step 7 of 13Compare
Three ways to run a project
| Aspect | Predictive (waterfall) | Agile | Hybrid |
|---|---|---|---|
| Planning | Detailed plan up front | High-level plan, detailed planning each cycle | Detailed for stable parts, adaptive for uncertain parts |
| Scope | Fixed early; changes go through formal change control | Evolves; reprioritized each cycle | Mixed |
| Delivery | One delivery near the end | Frequent working increments | Milestones plus increments |
| Customer involvement | Mainly at the start and at acceptance | Continuous | Varies by part |
| Best fit | Construction, manufacturing, regulated deliverables | Software, digital services, new products | Large programs mixing physical and digital work |
Step 8 of 13Practice · Sort into groups
Which approach fits each project best?
Tap an item, then tap its group (or drag it there).
Step 9 of 13Learn
Planning in waves
Even predictive projects can't plan everything in perfect detail on day one. Two ideas make planning realistic.
Progressive elaboration means the plan becomes more detailed and accurate as you learn more. Early estimates are rough; they're refined as design decisions are made and risks become clearer. This isn't a failure of planning; it's honest planning.
Rolling wave planning applies that idea to the schedule: plan the near-term work (the next few weeks or the next phase) in detail, and keep later work at a higher level until it gets closer. A six-month office relocation might have a detailed plan for the first month's lease negotiation and design work, while "move IT equipment" in month five stays a single line until the network design is known.
Both ideas share a principle with Agile: the plan is a tool, not a promise carved in stone. What matters is that the plan is realistic, that changes to it are deliberate and visible, and that stakeholders always know the current forecast.
A practical sign of healthy planning is how a team talks about dates. "We're aiming for May 15, with an 80% chance of finishing by May 29, and we'll firm it up after design" is more useful, and more honest, than a single date chosen to please someone.
Step 10 of 13Chart
The cone of uncertainty: why early estimates are ranges
At the idea stage, a well-run estimate can still be off by a factor of four in either direction. The range narrows as decisions are made, which is exactly what progressive elaboration relies on.
| Item | High end of range | Low end of range |
|---|---|---|
| Initial idea | 4 | 0.25 |
| Approved definition | 2 | 0.5 |
| Requirements done | 1.5 | 0.67 |
| Design done | 1.25 | 0.8 |
| Detailed design | 1.1 | 0.9 |
| Finished | 1 | 1 |
Step 11 of 13Practice · True or false
Monitoring and controlling is a phase that starts after all the work has been executed.
Step 12 of 13Practice · What would you do?
What would you do?
A city council wants a new online service for residents to report potholes. Nobody is sure which features residents will actually use, but the council wants something live within three months and is happy to improve it afterwards. Which approach should the project manager propose?
Step 13 of 13Practice · Choose one
In which process group is the project charter usually created and approved?