Module 4: Leading the WorkLesson 9 of 1213 min

Communication and Teams

Plan stakeholder communication, see why channels multiply as teams grow, write useful status reports, guide a team through its stages and handle conflict.

Step 1 of 13Learn

Planning communication

When stakeholders say a project "came out of nowhere" or "went quiet for months", the problem usually wasn't the work. It was communication. Project managers often say most of their job is communicating, and the best ones plan it as carefully as the schedule.

A communication plan answers, for each stakeholder group:

  • What do they need to know? Executives want progress against milestones, budget and major risks. The team needs task details and decisions.
  • When and how often? Weekly, at milestones, only when something changes.
  • How? Meeting, email, dashboard, shared workspace, one-to-one conversation.
  • Who sends it, and who is responsible for gathering the information?

Communication methods fall into three types:

  • Interactive: meetings, calls, workshops. Best for decisions, complex topics and sensitive news.
  • Push: sent to people (emails, reports, memos). Good for updates, but you can't be sure they were read or understood.
  • Pull: placed where people can find it when they want (a project site, a dashboard, a shared folder). Good for large audiences and reference material.

Match the method to the message. Never deliver bad news by a pushed report to someone who'll be upset; call them first. And remember the stakeholder grid from Module 2: high-power, high-interest stakeholders get interactive communication; the "monitor" group can pull information when they need it.

Step 2 of 13Compare

Three ways to communicate

AspectInteractivePushPull
ExamplesMeetings, calls, workshopsEmails, reports, memosProject site, dashboard, shared folder
Best forDecisions, complex or sensitive topicsRegular updates to known peopleLarge audiences, reference material
WeaknessTakes everyone's timeNo proof it was read or understoodPeople must remember to look
Typical audienceManage-closely stakeholdersKeep-informed groupsMonitor group

Step 3 of 13Learn

Why bigger teams talk more than you think

Every pair of people on a project is a potential communication channel, a path where information can be shared, misunderstood or lost. The number of channels grows much faster than the number of people:

Channels = n × (n − 1) / 2, where n is the number of people.

  • 3 people: 3 × 2 / 2 = 3 channels
  • 5 people: 5 × 4 / 2 = 10 channels
  • 10 people: 10 × 9 / 2 = 45 channels
  • 20 people: 20 × 19 / 2 = 190 channels

Doubling a team from 10 to 20 people more than quadruples the number of channels. That's one reason adding people to a late project can slow it down further: the new people need onboarding, and everyone spends more time coordinating.

The practical responses:

  • Keep core teams small. Many Agile frameworks recommend teams of about ten or fewer.
  • Create structure in larger projects: sub-teams with clear leads, so not everyone needs to talk to everyone.
  • Make information pullable: a single, current source of truth (a project page, a board, a decision log) reduces the need for one-to-one updates.
  • Write decisions down. Verbal agreements travel through channels and change along the way.

The formula counts people including the project manager, so when someone joins or leaves, the communication load changes for everyone.

Step 4 of 13Explore

Communication channels as a team grows

The curve shows n × (n − 1) / 2 for team sizes from 1 to 30. Move the slider to read the number of channels for a given team size.

0100200300400 102030
Channels for this team size
45
Channels if the team doubles
190
Channels added by one more person
10

Step 5 of 13Practice · Work it out

A project team has 8 people, including the project manager. How many communication channels are there?

Step 6 of 13Learn

Status reports and meetings that work

A good status report lets a busy sponsor understand the project in two minutes. Many organizations use a RAG status: Green (on track), Amber (at risk, being managed), Red (off track, needs help or a decision). A useful report contains:

  • Overall status and a one-sentence summary.
  • Progress against milestones: what was completed, what's next.
  • Schedule and budget position, ideally with forecasts (for example the EAC from earned value).
  • Top risks and issues, with owners and actions.
  • Decisions or help needed from the reader. This is the most important section and the most often missing.

Two warnings. First, avoid "watermelon reporting": green on the outside, red on the inside. Projects that report green for months and then suddenly turn red were rarely green. Report amber early; it's a request for attention, not a confession. Second, be specific: "Testing 2 weeks behind because the test environment was unavailable; recovery plan: weekend testing, back on track by May 20" beats "Some delays in testing."

Meetings are expensive: a one-hour meeting with eight people costs a full day of work. Make them count: a clear purpose, an agenda sent in advance, the right attendees, a time limit, and notes that record decisions and action items with owners and dates. If a meeting has no decision to make and no information that couldn't go in an email, cancel it.

Step 7 of 13Flashcards

Reading a RAG status

Tap a card to flip it.

Step 8 of 13Practice · Select all that apply

Which elements make a project status report genuinely useful to a sponsor? Select all that apply.

Select all that apply.

Step 9 of 13Learn

Building and leading the team

Most project teams are temporary groups of people who may never have worked together. Psychologist Bruce Tuckman described the stages teams typically pass through:

  1. Forming: polite, uncertain, looking to the leader for direction.
  2. Storming: disagreements surface about goals, roles and ways of working. Uncomfortable but normal.
  3. Norming: the team agrees on how to work together; trust grows.
  4. Performing: the team works effectively and largely manages itself.
  5. Adjourning: the project ends and the team disbands.

Teams don't always move neatly forward; a new member or a crisis can send them back to storming. The project manager's style should adapt: more direction during forming, active facilitation during storming, and more delegation once the team is performing.

Conflict is inevitable on projects, usually over schedules, priorities and resources rather than personalities. Common ways of handling it:

  • Collaborate / problem-solve: work together to find a solution that meets both sides' real needs. Best for important issues when there's time.
  • Compromise: each side gives something up. Quick, but nobody fully wins.
  • Smooth / accommodate: emphasize agreement and downplay differences. Preserves relationships for minor issues.
  • Force / direct: one person decides. Necessary in emergencies, damaging if overused.
  • Withdraw / avoid: postpone or step away. Useful to let tempers cool, harmful as a habit.

Step 10 of 13Practice · Put in order

Put Tuckman's stages of team development in order.

Drag the items, or use the arrow buttons, to put them in order.

  1. Norming
  2. Forming
  3. Storming
  4. Adjourning
  5. Performing

Step 11 of 13Practice · Diagram

Tuckman's stages and the leader's style

At which stage should the project manager step back and delegate the most?

Tap the shape that answers the question, then press Check.

Tuckman's stages and the leader's styleProcess diagram: Forming → Storming → Norming → Performing → Adjourning.FormingStormingNormingPerformingAdjourning
Forming

Give clear direction: goals, roles, ways of working.

Storming

Facilitate disagreements actively; they are normal.

Norming

Support the agreements the team makes.

Performing

Delegate; the team largely manages itself.

Adjourning

Recognize the work and help people move on.

Step 12 of 13Note

Step 13 of 13Practice · What would you do?

What would you do?

Two team leads are arguing about whether the testing team or the development team gets the only test environment next week. Both have valid deadlines, the disagreement is getting personal, and you have three days before it matters. What is the best approach?