Communication and Teams
Plan stakeholder communication, see why channels multiply as teams grow, write useful status reports, guide a team through its stages and handle conflict.
Welcome back!
Step 1 of 13Learn
Planning communication
When stakeholders say a project "came out of nowhere" or "went quiet for months", the problem usually wasn't the work. It was communication. Project managers often say most of their job is communicating, and the best ones plan it as carefully as the schedule.
A communication plan answers, for each stakeholder group:
- What do they need to know? Executives want progress against milestones, budget and major risks. The team needs task details and decisions.
- When and how often? Weekly, at milestones, only when something changes.
- How? Meeting, email, dashboard, shared workspace, one-to-one conversation.
- Who sends it, and who is responsible for gathering the information?
Communication methods fall into three types:
- Interactive: meetings, calls, workshops. Best for decisions, complex topics and sensitive news.
- Push: sent to people (emails, reports, memos). Good for updates, but you can't be sure they were read or understood.
- Pull: placed where people can find it when they want (a project site, a dashboard, a shared folder). Good for large audiences and reference material.
Match the method to the message. Never deliver bad news by a pushed report to someone who'll be upset; call them first. And remember the stakeholder grid from Module 2: high-power, high-interest stakeholders get interactive communication; the "monitor" group can pull information when they need it.
Step 2 of 13Compare
Three ways to communicate
| Aspect | Interactive | Push | Pull |
|---|---|---|---|
| Examples | Meetings, calls, workshops | Emails, reports, memos | Project site, dashboard, shared folder |
| Best for | Decisions, complex or sensitive topics | Regular updates to known people | Large audiences, reference material |
| Weakness | Takes everyone's time | No proof it was read or understood | People must remember to look |
| Typical audience | Manage-closely stakeholders | Keep-informed groups | Monitor group |
Step 3 of 13Learn
Why bigger teams talk more than you think
Every pair of people on a project is a potential communication channel, a path where information can be shared, misunderstood or lost. The number of channels grows much faster than the number of people:
Channels = n × (n − 1) / 2, where n is the number of people.
- 3 people: 3 × 2 / 2 = 3 channels
- 5 people: 5 × 4 / 2 = 10 channels
- 10 people: 10 × 9 / 2 = 45 channels
- 20 people: 20 × 19 / 2 = 190 channels
Doubling a team from 10 to 20 people more than quadruples the number of channels. That's one reason adding people to a late project can slow it down further: the new people need onboarding, and everyone spends more time coordinating.
The practical responses:
- Keep core teams small. Many Agile frameworks recommend teams of about ten or fewer.
- Create structure in larger projects: sub-teams with clear leads, so not everyone needs to talk to everyone.
- Make information pullable: a single, current source of truth (a project page, a board, a decision log) reduces the need for one-to-one updates.
- Write decisions down. Verbal agreements travel through channels and change along the way.
The formula counts people including the project manager, so when someone joins or leaves, the communication load changes for everyone.
Step 4 of 13Explore
Communication channels as a team grows
The curve shows n × (n − 1) / 2 for team sizes from 1 to 30. Move the slider to read the number of channels for a given team size.
- Channels for this team size
- 45
- Channels if the team doubles
- 190
- Channels added by one more person
- 10
Step 5 of 13Practice · Work it out
A project team has 8 people, including the project manager. How many communication channels are there?
Step 6 of 13Learn
Status reports and meetings that work
A good status report lets a busy sponsor understand the project in two minutes. Many organizations use a RAG status: Green (on track), Amber (at risk, being managed), Red (off track, needs help or a decision). A useful report contains:
- Overall status and a one-sentence summary.
- Progress against milestones: what was completed, what's next.
- Schedule and budget position, ideally with forecasts (for example the EAC from earned value).
- Top risks and issues, with owners and actions.
- Decisions or help needed from the reader. This is the most important section and the most often missing.
Two warnings. First, avoid "watermelon reporting": green on the outside, red on the inside. Projects that report green for months and then suddenly turn red were rarely green. Report amber early; it's a request for attention, not a confession. Second, be specific: "Testing 2 weeks behind because the test environment was unavailable; recovery plan: weekend testing, back on track by May 20" beats "Some delays in testing."
Meetings are expensive: a one-hour meeting with eight people costs a full day of work. Make them count: a clear purpose, an agenda sent in advance, the right attendees, a time limit, and notes that record decisions and action items with owners and dates. If a meeting has no decision to make and no information that couldn't go in an email, cancel it.
Step 7 of 13Flashcards
Reading a RAG status
Tap a card to flip it.
Step 8 of 13Practice · Select all that apply
Which elements make a project status report genuinely useful to a sponsor? Select all that apply.
Select all that apply.
Step 9 of 13Learn
Building and leading the team
Most project teams are temporary groups of people who may never have worked together. Psychologist Bruce Tuckman described the stages teams typically pass through:
- Forming: polite, uncertain, looking to the leader for direction.
- Storming: disagreements surface about goals, roles and ways of working. Uncomfortable but normal.
- Norming: the team agrees on how to work together; trust grows.
- Performing: the team works effectively and largely manages itself.
- Adjourning: the project ends and the team disbands.
Teams don't always move neatly forward; a new member or a crisis can send them back to storming. The project manager's style should adapt: more direction during forming, active facilitation during storming, and more delegation once the team is performing.
Conflict is inevitable on projects, usually over schedules, priorities and resources rather than personalities. Common ways of handling it:
- Collaborate / problem-solve: work together to find a solution that meets both sides' real needs. Best for important issues when there's time.
- Compromise: each side gives something up. Quick, but nobody fully wins.
- Smooth / accommodate: emphasize agreement and downplay differences. Preserves relationships for minor issues.
- Force / direct: one person decides. Necessary in emergencies, damaging if overused.
- Withdraw / avoid: postpone or step away. Useful to let tempers cool, harmful as a habit.
Step 10 of 13Practice · Put in order
Put Tuckman's stages of team development in order.
Drag the items, or use the arrow buttons, to put them in order.
- Norming
- Forming
- Storming
- Adjourning
- Performing
Step 11 of 13Practice · Diagram
Tuckman's stages and the leader's style
At which stage should the project manager step back and delegate the most?
Tap the shape that answers the question, then press Check.
- Forming
Give clear direction: goals, roles, ways of working.
- Storming
Facilitate disagreements actively; they are normal.
- Norming
Support the agreements the team makes.
- Performing
Delegate; the team largely manages itself.
- Adjourning
Recognize the work and help people move on.
Step 12 of 13Note
Step 13 of 13Practice · What would you do?
What would you do?
Two team leads are arguing about whether the testing team or the development team gets the only test environment next week. Both have valid deadlines, the disagreement is getting personal, and you have three days before it matters. What is the best approach?