Find a course

Module 2: Starting and Scoping a ProjectLesson 3 of 1212 min

Project Charter and Stakeholders

Write a project charter with SMART objectives, identify stakeholders, prioritize them with a power/interest grid, and clarify roles with a RACI chart.

Step 1 of 13Learn

The charter: a project's birth certificate

Jamal was asked to "sort out the customer onboarding process". Three weeks in, the sales director expected a new web form, the operations manager expected a full process redesign, and finance expected cost savings by June. Each had approved "the project" in a hallway conversation, and each imagined a different one.

A project charter prevents that. It is a short document, often one to three pages, that formally authorizes the project and records the essentials everyone must agree on:

  • Purpose and business case: why the project exists and what problem or opportunity it addresses.
  • Objectives and success criteria: measurable targets that define success.
  • High-level scope: the main deliverables, and what is explicitly excluded.
  • Key milestones and the target end date.
  • Summary budget.
  • Major risks, assumptions and constraints.
  • Key stakeholders.
  • The project manager's name and authority, and the sponsor's signature.

The sponsor's signature matters. It gives the project manager the authority to use resources and signals to the organization that the project is official.

A charter doesn't contain the detailed plan; it's the foundation the plan is built on. When disagreements appear later, as they always do, the charter is the agreed reference point: "Our objective was to cut onboarding time, not to redesign the CRM."

Step 2 of 13Compare

Jamal's project: hallway approval vs a signed charter

AspectHallway approvalSigned charter
What "the project" isEach person imagines their own versionOne written purpose and high-level scope
SuccessUnclear, argued about laterMeasurable objectives agreed up front
AuthorityNobody sure who can decideNamed sponsor and project manager
Budget and datesAssumed differently by each managerSummary budget and key milestones
Three weeks inWeb form vs redesign vs cost savingsDisagreements surfaced before work started

Step 3 of 13Learn

SMART objectives

"Improve customer onboarding" is a wish, not an objective. You can't plan for it, and you'll never know if you achieved it. Good project objectives are SMART:

  • Specific: clear about what will change. Reduce onboarding time for new business customers.
  • Measurable: has a number you can check. …from 10 days to 3 days.
  • Achievable: realistic with the time and resources available.
  • Relevant: connected to the business case and the organization's goals.
  • Time-bound: has a deadline. …by September 30.

Put together: "Reduce average onboarding time for new business customers from 10 working days to 3 by September 30, measured from signed contract to first login."

Notice the last phrase: it defines exactly how the number will be measured. Without it, people may argue later about whether onboarding starts at the first call, the signed contract or the invoice.

Common mistakes:

  • Activities instead of results: "Implement a new CRM" is a deliverable, not an objective. Why are you implementing it? What should improve?
  • Unmeasurable adjectives: "user-friendly", "modern", "world-class".
  • Too many objectives: a project with twelve objectives effectively has none. Three to five is typical.

Step 4 of 13Practice · Spot the mistake

A draft charter lists these objectives. Tap the ones that are not SMART.

Step 5 of 13Learn

Who cares about this project?

A stakeholder is anyone who affects or is affected by the project. Missing an important one is a classic cause of late surprises: the IT security team that blocks your launch, or the union representative who learns about a process change from a rumor.

Start by brainstorming broadly: sponsor, team, users, customers, suppliers, other departments, regulators, the people whose daily work will change. Record them in a stakeholder register with their role, interest, influence and expectations.

Then prioritize with a power/interest grid, which places each stakeholder by how much power (authority or influence) they have over the project and how much interest (concern or impact) they have in it:

Low interestHigh interest
High powerKeep satisfied: regular summaries, consult on major decisionsManage closely: engage actively and often
Low powerMonitor: occasional general updatesKeep informed: regular updates, listen to concerns

A CFO who controls funding but isn't involved day to day is high power, low interest: keep satisfied with concise updates. The customer service agents who will use a new system every day are high interest, but individually low power: keep informed, and involve some of them in testing.

Stakeholders move around the grid. A regulator who ignores your project for months may become very interested the week before launch. Review the register regularly.

Step 6 of 13Practice · Sort into groups

Place each stakeholder of a new hospital scheduling system on the power/interest grid.

Tap an item, then tap its group (or drag it there).

Step 7 of 13Practice · Diagram

The power/interest grid

A regulator can block your launch but pays no attention to the project until the final inspection. Where does it belong?

Tap the shape that answers the question, then press Check.

The power/interest gridTwo-by-two matrix: Keep satisfied, Manage closely, Monitor, Keep informed.Keep satisfiedManage closelyMonitorKeep informedInterest in the projectLowHighPower over the projectLowHigh
Keep satisfied

High power, low interest: short regular summaries, consult on major decisions.

Manage closely

High power, high interest: engage actively and often, usually face to face.

Monitor

Low power, low interest: light-touch updates they can pull when needed.

Keep informed

Low power, high interest: regular updates, listen for concerns and ideas.

Step 8 of 13Learn

RACI: who does what

"I thought you were doing that" is one of the most expensive sentences in project management. A RACI chart (or responsibility assignment matrix) prevents it by listing tasks or decisions down the side, people or roles across the top, and one letter in each relevant cell:

  • R, Responsible: does the work. There can be several.
  • A, Accountable: owns the result and signs off. There must be exactly one per task.
  • C, Consulted: gives input before the work is done (two-way communication).
  • I, Informed: told about progress or decisions (one-way communication).
TaskSponsorProject managerDesignerIT lead
Approve budgetARI
Design the formIARC
Configure the serverACR
Approve go-liveARIC

Rules of thumb when reviewing a RACI chart:

  • Exactly one A per row. Two As means nobody is really accountable; zero As means decisions stall.
  • Every row needs at least one R. Otherwise nobody does the work.
  • Too many Cs slow everything down. Not everyone needs to be consulted on everything.
  • A column full of As or Rs reveals an overloaded person.

Agree the chart with the people in it. A RACI that only the project manager has seen is a wish list.

Step 9 of 13Practice · Choose one

A RACI chart for "Choose the new payroll vendor" shows the HR director as A, the finance director as A, and two analysts as R. What is the main problem?

Step 10 of 13Flashcards

The four RACI letters

Tap a card to flip it.

Step 11 of 13Note

Step 12 of 13Practice · Select all that apply

Which items belong in a project charter? Select all that apply.

Select all that apply.

Step 13 of 13Practice · Fill in the blanks

Fill in the blanks

SMART stands for Specific, , Achievable, Relevant and .