Managing Risk
Tell risks from issues, write clear risk statements, rank risks by probability and impact, calculate expected monetary value, and choose the right response.
Welcome back!
Step 1 of 13Learn
Risks are problems that haven't happened yet
Two weeks before a product launch, the payment provider announces a planned outage on launch day. One project manager scrambles. Another opens the risk register, finds "payment provider unavailable" already listed with a backup provider tested and ready, and switches over in an afternoon.
A risk is an uncertain event or condition that, if it occurs, affects at least one project objective. An issue is a problem that is happening now. Risk management is about dealing with tomorrow's issues while they're still cheap to handle.
Risks can be negative (threats: a key supplier goes bankrupt) or positive (opportunities: a new tool could cut testing time in half). Good risk management looks for both.
The process is a loop that runs for the whole project:
- Identify risks.
- Analyze them: how likely, how much impact?
- Plan responses for the most important ones and assign an owner to each.
- Implement the responses when needed.
- Monitor: review the list regularly, close old risks, add new ones.
Everything is recorded in a risk register: a simple table with each risk's description, probability, impact, score, owner, response and status. A register that's created at kickoff and never opened again is worse than useless; it gives false comfort. Make risk review a standing item in team meetings.
Step 2 of 13Practice · Sort into groups
Sort each statement as a risk (might happen) or an issue (happening now).
Tap an item, then tap its group (or drag it there).
Step 3 of 13Learn
Identifying risks
You can't manage risks you haven't spotted. Useful identification techniques include:
- Brainstorming with the team and key stakeholders. Different specialists see different dangers.
- Checklists and lessons learned from past projects: what went wrong last time?
- Assumption analysis: every assumption in the charter or scope statement is a potential risk. "Marketing will supply text by May 1" becomes "Marketing may deliver text late."
- Expert interviews with people who've done similar work.
- Walking the WBS: go branch by branch and ask what could go wrong in each.
Write each risk in a way that makes it actionable. A helpful format is the cause, event, effect statement:
Because [cause], [event] may occur, which would lead to [effect].
Compare "Vendor risk" with: "Because the vendor is also supplying two larger clients this quarter, delivery of our servers may slip by two or more weeks, which would delay system testing and the go-live date." The second version tells you what to watch (the vendor's other commitments), what to plan for (a slip of two weeks) and why it matters (it hits the critical path).
Vague risks like "budget" or "resources" can't be owned or managed. If a risk can't be stated with a cause and an effect, keep asking "why?" until it can.
Step 4 of 13Diagram
The risk management loop
Tap a shape with to see more.
- Identify
Brainstorm, checklists, assumptions, walk the WBS.
- Analyze
Rate probability and impact; rank the list.
- Plan responses
Choose a strategy and a risk owner for each important risk.
- Implement
Carry out the responses, or trigger contingency plans.
- Monitor
Review the register regularly; new risks appear and old ones close.
Step 5 of 13Learn
Analyzing risks: probability, impact and EMV
You'll identify far more risks than you can actively manage, so you rank them. The usual tool is a probability and impact matrix. Rate each risk's probability and impact, often on a 1 to 5 scale, and multiply for a score:
| Risk | Probability (1-5) | Impact (1-5) | Score |
|---|---|---|---|
| Server delivery slips 2+ weeks | 3 | 5 | 15 |
| Venue double-booked | 1 | 5 | 5 |
| Minor UI changes requested | 5 | 1 | 5 |
High scores get detailed responses; low scores are watched. Define the scales in advance ("impact 5 = delay over 4 weeks or cost over 10%") so ratings are consistent between people.
When you can estimate numbers, expected monetary value (EMV) turns a risk into money:
EMV = probability × impact
A 20% chance of a $50,000 penalty has an EMV of 0.20 × $50,000 = $10,000. Opportunities have positive EMV, threats negative. EMV is useful for two decisions:
- Sizing contingency: the sum of the EMVs of your identified threats gives a reasoned starting point for the contingency reserve.
- Judging responses: spending $4,000 to cut the probability of that penalty from 20% to 5% reduces EMV from $10,000 to $2,500, a $7,500 improvement for $4,000. Worth it.
Remember that EMV is an average across many possible outcomes. A single catastrophic risk with low probability may still deserve attention beyond its EMV.
Step 6 of 13Practice · Chart
Risks plotted by probability and impact
Risks toward the top right deserve the most attention. Score = probability × impact.
Which risk has the highest probability × impact score?
Tap the point that answers the question, then press Check.
| Point | Probability (1-5) | Impact (1-5) |
|---|---|---|
| Server delivery slips | 3 | 5 |
| Venue double-booked | 1 | 5 |
| Minor UI changes | 5 | 1 |
| Key developer leaves | 2 | 4 |
| Permit delayed | 4 | 3 |
Step 7 of 13Try the calculator
Expected monetary value of a threat
Compare a risk's EMV before and after a mitigation, and see whether the mitigation pays for itself.
- EMV before = p × impact
- 10,000 $
- EMV after mitigation
- 2,500 $
- Reduction in EMV
- 7,500 $
- Net benefit of mitigating (reduction − cost)
- 3,500 $
Step 8 of 13Practice · Work it out
A risk has a 30% chance of causing $40,000 in extra costs. What is its expected monetary value, in dollars (ignore the sign)?
Step 9 of 13Learn
Planning risk responses
For each significant risk, choose a response strategy and assign a risk owner, the person who watches it and acts.
For threats:
- Avoid: change the plan to eliminate the threat. Drop a risky feature, choose a proven technology, move an outdoor event indoors.
- Transfer: shift the financial impact to a third party. Insurance, warranties, fixed-price contracts with penalties. The risk still exists; someone else pays if it happens.
- Mitigate: reduce the probability or impact. Prototype early, add testing, train staff, order critical parts sooner, arrange a backup supplier.
- Accept: acknowledge the risk and do nothing in advance, either passively (deal with it if it happens) or actively, by setting aside contingency time or money and preparing a contingency plan with a trigger ("if the vendor misses the May 1 checkpoint, switch to supplier B").
- Escalate: when the threat is outside the project's authority, such as a company-wide policy change, pass it to the right level of management.
For opportunities:
- Exploit: make sure it happens. Assign your best expert to finish early and win a bonus.
- Enhance: increase its probability or benefit.
- Share: partner with someone better placed to capture it, and split the benefit.
- Accept: take the benefit if it comes, without extra effort.
Responses cost time and money, so match the effort to the risk's score. And responses can create secondary risks: a backup supplier may have its own quality problems.
Step 10 of 13Practice · Match the pairs
Match each action to the risk response strategy it represents.
Tap an answer, then tap the place where it belongs (or drag it there).
- Buying event cancellation insurance
- Replacing an untested new framework with a proven one
- Running a pilot with 20 users before rolling out to 2,000
- Setting aside two weeks of buffer in case permits are late
- Partnering with a supplier to jointly bid for a larger contract
Step 11 of 13Diagram
Risk response strategies at a glance
Tap a shape with to see more.
- Risk responses
- Threats
- Opportunities
- Avoid
Change the plan so the threat cannot happen.
- Transfer
Someone else bears the financial impact.
- Mitigate
Reduce probability or impact.
- Accept
Do nothing now, or set aside contingency with a trigger.
- Escalate
Outside the project's authority: pass it up. Also used for opportunities.
- Exploit
Make sure the opportunity happens.
- Enhance
Raise its probability or benefit.
- Share
Partner with someone better placed and split the benefit.
- Accept
Take the benefit if it comes.
Step 12 of 13Practice · What would you do?
What would you do?
An outdoor product launch event is planned for October. Weather records show a 40% chance of heavy rain on any given October day, and rain would ruin the event. The venue offers an indoor hall at extra cost, which must be booked two months in advance. What is the most sensible response?
Step 13 of 13Practice · True or false
Buying insurance against a project risk is an example of transferring the risk.
Lesson complete!